Deadlines for actions required for exemption
Or. Rev. Stat. § 307.637
in effect307.637. Deadlines for actions required for exemption
An exemption for multiple-unit housing may not be granted under ORS 307.600 to 307.637 unless:
(1) In the case of multiple-unit housing described in ORS 307.603 (5)(a), the application for exemption is made to the city or county on or before January 1, 2032.
(2) In the case of multiple-unit housing described in ORS 307.603 (5)(b), the construction, addition or conversion is completed on or before January 1, 2032.
Formerly 307.691; 2011 c.266 §4; 2019 c.322 §1
Source: Oregon Legislature (oregonlegislature.gov)URL: https://www.oregonlegislature.gov/bills_laws/ors/ors307.html#307.637Fetched: 10/20/2026