21-0705. - Issuance of permit—Procedure.

Upon submission of an application for a permit, the building inspector shall examine said application and, if the proposed WECS complies will all the terms and provisions of this ordinance, shall issue the permit. Provided, that if there is any property within the TCA which is not zoned in accordance with § 21-0703 of this article, or if the proposed installation is on a lot which is adjacent to a residential zone, no permit may be issued without prior approval of the planning commission as hereinafter provided. Application for approval of the planning commission shall be made by the applicant by submission of a duplicate copy of his application to the planning commission office. Upon receipt of such application, the planning commission shall consider the matter at its next regularly scheduled meeting and shall either approve or deny the application. In the event the planning commission does not take action on the application within 40 days of date of submission, the application shall be deemed to be approved and the building inspector may issue the permit if all other requirements have been met.

Source: 2166 (1984).