§ 98-118 — Performance criteria for stormwater management
Code of Ordinances, City of Oxford, Mississippi (Supp. No. 36: codified through Ordinance No. 2026-5, enacted March 17, 2026) · Oxford Code of Ordinances § 98-118
Corpus is an independent public-information project, not the official City of Oxford website. Stable reference: corpuslaw.us/code/d5227bf2-6b69-4cd7-be23-f86a10018972
Sec. 98-118. - Performance criteria for stormwater management.
(a) Generally. (1) All new development and redevelopment shall comply with Article IV, Erosion Control of Chapter 98. (2) The following performance criteria apply to all new developments. (3) Redevelopment is subject to the following performance criteria with an exception: At the discretion of the city engineer, pre-development runoff rate calculations may count impervious cover areas as impervious cover rather than a natural condition. (b) Limitation on stormwater runoff calculations. The stormwater management facility will be designed so that, except in unusual circumstances, the rate of runoff of surface water from the site, in the condition in which it is proposed to be developed, will not exceed the rate of runoff from the site in its undeveloped or natural condition as generated by the 2-year, 10-year, and 25-year storm events. Runoff rates and volumes shall be calculated using the soil conservation service (SCS) method. The rational method is not acceptable for storage volume calculations. The rational method may only be used for pipe conveyance calculations. For the SCS method, a type II rainfall distribution and a shape factor of 483.4 (484) will be used. The 24-hour duration precipitation frequency values to be used with the SCS method are 4.25 inches for the 2-year storm, 5.92 inches for the 10-year storm, 7.01 inches for the 25-year storm, and 8.75 inches for the 100-year storm. Time of concentration (Tc) shall be estimated using the methods given in the U.S. Department of Agriculture, National Resources Conservation Service, Part 630 National Engineering Handbook, Chapter 15, Time of Concentration, 630.1502 Methods for Estimating Time of Concentration. The watershed lag method may not be used to estimate the time of concentration for urbanized site conditions. A minimum time of concentration of five minutes will be used for storage volume calculations. (c) Storage capacity. Stormwater management facilities shall be designed with sufficient capacity to accommodate all runoff caused by the development more than that runoff which would occur from the site if left in its natural, undeveloped condition. This storage shall accommodate excess runoff for the 2-year, 10-year, and 25-year storms of 24-hour duration. (d) Discharge rate. The peak flow (Q year ) shall be calculated for the 2-year, 10-year, and 25-year storms. The cumulative peak flow for the development, runoff captured by stormwater management facilities plus uncaptured runoff, must be less than or equal to the cumulative peak flow for the site if left in its natural condition. The peak flows shall not be increased at any discharge point, including areas of uncaptured runoff, for any storm up to and including the 25-year storm (Q 25 ). (e) Energy dissipation. All culvert outlets and flumes must have energy-dissipating treatments to minimize erosion due to scouring and maintain channel stability. Approved energy dissipating treatments include stilling basins, streambed level dissipators, riprap basins, and aprons. All energy dissipating treatments shall be designed by design criteria outlined in U.S. Department of Transportation, Federal Highway Administration, Hydraulic Engineering Circular No. 14, Third Edition Hydraulic Design of Energy Dissipators for Culverts and Channels. Supporting design calculations shall be included as part of the stormwater management plan. (f) Point of discharge. A surface outlet for a stormwater management facility's control structure cannot discharge within 40 feet of an adjacent property line unless a formal and perpetual drainage easement to discharge onto or across the adjoining property is provided or conditions warrant special consideration. The city engineer may give special consideration to discharge into a significant receiving stream, provided provisions are taken to ensure that the integrity of the receiving stream is protected. If the pre-developed site consists of multiple drainage basins, post-development discharge cannot exceed the discharge rate of the pre-development basins. (g) Conveyance. Storm drainage components shall be designed to remove excess runoff from precipitation and convey it to a stormwater management facility with minimum inconvenience, life hazard, and property damage. These components include curb and gutter areas of the street, roadside ditches, inlets, storm sewers, culverts, channels, or other conveyances and shall be designed to convey the runoff from the 25-year storm. (h) Stormwater management facilities in floodplains. Suppose a stormwater management facility is located within a floodplain of a significant stream. In that case, no storage volume for the facility may be provided below the base flood elevations established for that floodplain. The city engineer may give special consideration if no alternate location of the stormwater management facility is practical. (i) Stormwater bypass. Storm drainage components shall have adequate capacity to convey flow from all upstream areas through the development. (j) Stormwater Management—Construction. Stormwater management shall be implemented during all stages of site development. Stormwater management facilities shall be implemented as part of the initial land disturbance activities and incorporated into developing a stormwater pollution prevention plan. Erosion control measures such as stormwater retention devices or sediment traps may be used as temporary stormwater management facilities during the development construction process. At a minimum, a temporary stormwater management facility must be capable of managing runoff from 2-year and 10-year storm events. Stormwater management facilities, permanent or temporary, must be adequately maintained during all stages of site development. (k) Stormwater management—Phased development. The stormwater management facilities shall be designed for phased developments so that the development complies with this article at the end of each phase. As additional phases are developed, the stormwater management facilities may be expanded, control structures modified, and new stormwater facilities constructed to account for changes in site conditions. (l) Detention basins. (1) The maximum designed depth of stormwater stored shall not exceed eight feet. A minimum of 0.5 feet of freeboard shall be provided, measured from the top of the peak water surface elevation for the 25-year storm event to the lowest point on the top of the pond, excluding the emergency spillway invert. (2) All dams or dikes shall be designed and constructed according to accepted engineering standards. (3) The exterior slopes of the basin shall conform as closely as possible to natural land contours. Regrading is allowable if necessary to keep exterior slopes at 4H:1V or flatter. (4) Interior basin slopes shall be 3H:1V or flatter. (5) Detention basins may use vertical interior walls by special exception. The maximum interior height of a vertically walled detention pond is eight feet, and it is built in four-foot-high segments. The height measurement shall not include parts of a wall below the ground surface. A safety ledge a minimum of three feet wide shall separate segments. (6) Detention basins with vertical interior walls shall have emergency egress steps or ladders. (7) Detention basin bottoms shall have a minimum width of two feet per one foot of depth. (8) Emergency spillway/overflow facilities shall be provided to pass runoff more than the 25-year storm event up to the 100-year storm event unless positive measures are installed to control the inflow so as not to exceed the safe capacity of the basin. Emergency spillways shall be protected with concrete or grouted riprap. (9) The detention basin bottom shall have a concrete-lined low-flow channel between inflow points and the outlet structure. The low-flow channel shall have a minimum slope of 0.5% between all inflow points and the outlet structure. (10) The detention basin bottom shall have a minimum cross slope of 1.0% perpendicular to the low-flow channel. (11) All detention basins shall use a solid sod or seed for the final cover. The sod and seed variety should be suitable for wet locations. Mass grading of the pond bottom should account for the thickness of the sod so that the final design of pond bottom elevation and slopes are achieved. Any areas of sod that die within two months of placement shall be removed and replaced. If a seed is used, germination should occur within 14 days, and 80 percent coverage should be achieved within two months. If coverage is not achieved with seeding, then at the discretion of the city engineer, solid sod may be required. (12) Detention basins shall be designed to drain completely and not retain standing water 48 hours after a storm event. A detention basin that fails to drain within this period shall violate this article subject to the enforcement provisions and penalties outlined. (13) Detention basins shall be enclosed by a fence when required by the city engineer. (m) Underground basin. (1) Adequate maintenance access must be provided for all underground basins. All underground basins shall give access to the inlet end and outflow structure. Access openings include a standard manhole, grate, solid cover, or a removable panel. (2) Underground basins shall be considered confined spaces and treated as such for entry purposes. (3) Underground basins shall be evaluated for 100-year storm events to ensure no unintended consequences due to the discharge routing when the underground basin exceeds storage capacity. (4) Watertight underground basins shall have a minimum slope of 0.5% between the highest invert point of the storage chamber and the outlet structure. Non-watertight underground basins that can infiltrate water through the bottom of the storage chambers may be designed with a zero slope. (5) Underground basins shall be designed to drain completely and not retain standing water 48 hours after a storm event. An underground detention basin that fails to drain within this period shall violate this article, subject to the enforcement provisions and penalties outlined. (n) Retention basin. (1) The maximum designed depth of stormwater stored shall not exceed eight feet. A minimum of 0.5 feet of freeboard shall be provided, measured from the top of the peak water surface elevation for the 25-year storm event to the lowest point on the top of the pond, excluding the emergency spillway invert. (2) The depth of the permanent pool, before the introduction of excess stormwater, shall be greater than three feet. The minimum depth of the permanent pool must be maintained year-round. An irrigation water source may be required to maintain the minimum pool depth for retention basins not situated on a perennial stream. (3) Aeration facilities may be required, depending on the water quality of the static pool and at the discretion of the city engineer. (4) All dams or dikes shall be designed and constructed according to accepted engineering standards. (5) The interior slopes of the retention basin shall be of non-erosive material. For retention basins with interior side slopes steeper than 4H:1V or a static pool depth of four feet or greater, the perimeter shall be surrounded by safety and aquatic benches. A safety bench shall extend approximately five feet outward from the standard water edge to the toe of the pond side slope. An aquatic bench shall extend approximately five feet inward from the standard pool edge. The benches shall have a 10H:1V slope. (6) By special exception, retention basins may use vertical interior walls. The maximum interior height of a vertically walled retention basin is eight feet, and it is built in four-foot-high segments. The height measurement shall not include parts of a wall below the ground surface. A safety ledge a minimum of three feet wide shall separate segments. (7) Retention basins with vertical interior walls shall have emergency egress steps or ladders. (8) Retention basins shall have a minimum length-to-width ratio of 1.5:1. The length shall be measured at the shortest flow path from the inlet to the outlet. The location of the outlet structure within the basin shall maximize travel time from the inlet to the outlet. (9) Emergency spillway/overflow facilities shall be provided to pass runoff more than the 25-year storm event up to the 100-year storm event unless positive measures are installed to control the inflow so as not to exceed the safe capacity of the basin. Emergency spillways shall be protected with concrete or grouted riprap. (10) For emergency purposes, cleaning, or shoreline maintenance, retention basins shall be provided with equipment and devices to permit emptying and drainage of the permanent pool. (11) All slopes of retention basins above the static water elevation shall use a solid sod or seed for the final cover. The sod and seed variety should be suitable for wet locations. Any areas of sod that die within two months of placement shall be removed and replaced. If seed is used, germination should occur within 14 days, and 80 percent coverage should be achieved within two months. If coverage is not achieved with seeding, then at the discretion of the city engineer, solid sod may be required. (12) Non-invasive, native aquatic plants and trees may be used along the submerged portion of the safety bench. An approved planting plan is required. (13) Retention basins shall be enclosed by a fence when required by the city engineer. (14) Retention basins shall be subject to the City of Oxford's mosquito control ordinance requirements. (o) Outlet control structures. (1) Outlet control structures shall be designed as simply as possible, with automatic operation, ensuring ease of construction or manufacturing to the stormwater facility's engineering specifications. A weir plate is recommended to simplify the implementation process. Outlet control structures shall use a steel weir plate when circular orifices are specified. No weir plate or riser orifice shall be fabricated in the field. (2) Outlet control structures shall be designed for multi-stage release to limit discharges into existing or planned downstream channels or conduits so as not to exceed predetermined safe capacities and not more than flows that would have occurred with the site in its natural, undeveloped condition for the 2-year, 10-year, and 25-year storms. (3) Outlet control structures shall have no orifice smaller than three inches in diameter. Trash racks shall protect all orifices. No opening in the trash rack shall have an area more than one-half the size of the area of the orifice being protected. Two-stage trash racks, or screens having progressively smaller openings placed in series, are suggested. Curved or inclined trash racks that allow debris to rise with the water level are preferred. In all cases, trash racks shall be hinged or removable to facilitate maintenance operations. An anti-vortex device and trash rack shall be securely installed on the riser for vertical risers. (4) Energy dissipation measures shall be employed to ensure that discharge from an outlet control structure does not increase downstream erosion.
(Ord. No. 2018-14, 8-21-2018; Ord. No. 2024-8, § I, 6-4-2024)