Sec. 40-159. - Completion of excavation; warranty.
(a) In accordance with the rules and regulations promulgated under section 40-128 of this Code, a permittee shall notify the city engineer before commencing and obtain permission to commence the excavation before it enters into the public way. In connection with the notification and permission, the authorized date of entry on the public way, for purposes of section 40-138(c)(5) of this Code shall be established. In connection with the notification, the permittee shall also furnish the transmittal number required under section 40-136(b)(13) of this Code, if it has not previously been provided. The permittee shall diligently prosecute the excavation to its final completion within the time authorized under the permit. It shall be unlawful for a permittee to fail, refuse or neglect to diligently prosecute or to timely complete the excavation in accordance with the permit and all applicable rules and regulations and the construction standards adopted in or pursuant to this article. (b) If a permittee commences an excavation and then fails, refuses, or neglects to diligently prosecute or to timely complete the excavation in accordance with the permit and all applicable rules and regulations and the construction standards adopted in or pursuant to this article, the city engineer may, following written notice to the permittee, perform the excavation or cause a city contractor to perform the excavation. The city engineer shall afford the permittee five days' written notice and opportunity to cure before taking over the excavation, unless the Director of Houston Public Works determines that hazards to public safety and convenience that are posed by the condition of the excavation require a shorter notice period. The city engineer may charge the cost of having the excavation performed, including related administrative expenses, to the permittee. The city engineer shall so notify the permittee, and the permittee shall be obliged to pay the cost within 30 days following receipt of notification. Disputes over costs assessed shall be subject to the hearing process established under section 40-126 of this Code.
(Ord. No. 00-1115, § 2, 12-20-00; Ord. No. 06-595, §§ 16, 17, 6-7-06; Ord. No. 2018-11, § 49, 1-10-2018)
Ask a question about Houston law
Corpus searches the Houston sections it holds and shows the ones that match, with their citations. Free, no sign-in.