§ 17-236 — Removal, Relocation or Modification of Network Nodes in the ROW
Code of Ordinances of the City of Tyler, Texas (September 2026: including amendments through September 9, 2026) · Tyler City Code § 17-236
Corpus is an independent public-information project, not the official City of Tyler website. Stable reference: corpuslaw.us/code/d5e01925-4409-4420-abec-ef612daa944d
Sec. 17-236. Removal, Relocation or Modification of Network Nodes in the ROW
(A) Notice. Within 90 days following written notice from the City, a Network Provider shall, at its own expense, protect, support, temporarily or permanently disconnect, remove, relocate, change or alter the position of any Network Node or Node Support Pole within the public right-of-way whenever the City has determined that such removal, relocation, change or alteration, is reasonably necessary for the construction, repair, maintenance, or installation of any City improvement in or upon, or the operations of the City in or upon, the public right-of-way. (B) Emergency Removal or Relocation of Facilities. The City retains the right and privilege to disconnect or move any Network Node located within the public right-of-way of the City, as the City may determine to be necessary, appropriate or useful in response to any public health or safety emergency. If circumstances permit, the City shall notify the Network Provider and allow the Network Provider an opportunity to move its own facilities prior to the City disconnecting or removing a facility and shall notify the Network Provider after disconnecting or removing a Network Node or Node Support Pole. (C) Street widening or straightening. Consistent with Texas Utilities Code § 54.203(c), upon thirty (30) days' notice by the City, a Network Provider shall begin relocation of its facilities within the rights-of-way at its own expense to permit the widening or straightening of streets. The notice by the City shall include a specification of the new location for the Network Provider's facilities along the rights-of-way. (D) Abandonment of Facilities. A Network Provider may not abandon its facilities in a public right of way. If a Network Provider stops use of a Network Node or Node Support Pole for 120 consecutive days it shall be deemed abandoned and must be removed by the Network Provider at its sole expense within 60 days of such abandonment. Except that a Network Provider is not required to and shall not remove any Node Support Pole that has been abandoned by the Network Provider but is in Collocation use by another Network Provider. The Network Provider shall give the City written notice of all abandoned facilities and its plan for removal of such facility at least 30 days prior to any removal. Following the removal of any facility the Network Provider shall leave the right-of-way in the same or substantially the same condition as it was prior to the installation of the facility
Ask a question about Tyler law
Corpus searches the Tyler sections it holds and shows the ones that match, with their citations. Free, no sign-in.