Design-build or construction management contracts.
Norfolk City Code § 33.1-59
in effectSec. 33.1-59. - Design-build or construction management contracts.
While the competitive sealed bid process remains the preferred method of construction procurement, the city may enter into a contract for construction on a fixed-price or not-to-exceed price design-build or construction-management basis, provided the city complies with the requirements of this section adopts a resolution or ordinance on a per project basis prior to issuing a request for qualifications; complies with Virginia Code § 2.2-4382, and has by ordinance or resolution implemented procedures consistent with the procedures adopted by the secretary of administration for utilizing construction-management or design-build contracts.
Prior to making a determination as to the use of design-build or construction management for a specific construction project, the city shall have in its employ or under contract a licensed architect or engineer with professional competence appropriate to the project who shall advise the city regarding the use of design-build or construction management for that project and who shall assist the city with the preparation of the request for proposals and the evaluation of such proposals.
Prior to issuing a request for qualifications for any design-build or construction-management contract for a specific construction project, the city shall:
(1) Document in writing that, for a specific construction project:
(a) A design-build or construction-management contract is more advantageous than a design-bid-build construction contract;
(b) There is a benefit to the city to using a design-build or construction-management contract;
(c) Design-bid-build is not practical or fiscally advantageous, and
(d) The project's complexity requires the need to utilize the design-build or construction-management method.
(2) Include the written determination in the request for qualifications and maintain it in the procurement file.
(3) Have adopted, by ordinance or resolution, written procedures governing the selection, evaluation, and award of construction-management and design-build contracts consistent with the procedures adopted by the secretary of administration, which procedures shall include all of the following:
(a) Requests for proposals shall include and define the criteria for the construction project in areas such as site plans; floor plans; exterior elevations; basic building envelope materials; fire protection information plans; structural, mechanical (HVAC), and electrical systems; and special telecommunications; and may define other such requirements as the city determines appropriate for that particular construction project;
(b) Construction-management or design-build may be utilized on projects provided that the project is complex and the procurement method for the project is approved by resolution or ordinance;
(c) Design-build construction projects shall include a two-step competitive negotiation process consistent with the standards established by the Virginia Department of General Services, Division of Engineering and Building;
(d) Construction-management projects shall include selection procedures and required contract terms consistent with the regulations established by the Virginia Secretary of Administration and the Department of General Services, Division of Engineering and Building;
(e) Public notice of the request for qualifications shall be posted on the department's central electronic procurement website or the city's website at least thirty (30) days prior to the date set for receipt of qualification proposals;
(f) Construction-management contracts to be entered into no later than the completion of the schematic phase of design, unless prohibited by authorization of funding restrictions;
(g) Prior construction management or design-build experience shall not be considered a prerequisite or factor considered for prequalification of a contract. However, in the selection of a contractor, city may consider the experience of each contractor on comparable construction- management or design-build projects;
(h) Construction-management contracts shall require that no more than ten (10) percent of the construction work, as measured by the cost of the work, be performed by the construction manager with its own forces and the remaining ninety (90) percent of the construction work, as measured by the cost of the work, be performed by subcontractors of the construction manager, which the construction manager shall procure by publicly advertised, competitive sealed bidding to the maximum extent practicable.
(i) The procedures are required to allow a two-step competitive process;
(j) Price is a critical basis for award of the contract; and
(k) Be authorized to post on an electronic website, or the city's own website, when and where the general contractor plans to advertise bid packages for subcontracting opportunities.
(Ord. No. 43,223, § 2, 9-9-08; Ord. No. 50,127, § 2, 9-23-25)
Source: City of Norfolk, Virginia, City Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/va/norfolk/codes/code_of_ordinances?nodeId=COCI_CH33.1PR_ARTVSP_S33.1-59DEILCOMACOFetched: 11/1/2026