Payments applied first to preconstruction lien.
Utah Code § 38-1a-305
in effect38-1a-305. Payments applied first to preconstruction lien.
Unless an agreement waiving or limiting a right under a preconstruction or construction lien expressly provides that a payment is required to be applied to a specific lien, mortgage, or encumbrance, a payment to a person claiming both a preconstruction lien and a construction lien shall be applied first to the preconstruction lien until paid in full.
Enacted by Chapter 278, 2012 General Session
Source: Utah Office of Legislative Research and General Counsel (le.utah.gov)URL: https://le.utah.gov/xcode/Title38/Chapter1A/38-1a-S305.html?v=C38-1a-S305_1800010118000101Fetched: 10/26/2026