Inspection; certificate of approval.
Biloxi Code of Ordinances § 5-5-13
in effectSec. 5-5-13. - Inspection; certificate of approval.
(a) Upon completion of the work which has been authorized by issuance of any permit under this article, it shall be the duty of the contractor installing the work to notify the plumbing inspector's office, which shall inspect the installation within 16 "working hours" (defined for purposes of this section as hours between 7:30 a.m. and 4:30 p.m. on weekdays, excluding municipal holidays). All work must be left uncovered and convenient for examination until inspected and approved.
(b) Where the plumbing inspector finds the installation to be in conformity with the provisions of this article, he shall issue to the contractor making the installation a certificate of approval, or he may, at his election, affix to the property a notice that an inspection has been made and the work installed is approved, authorizing the use of the installation and connection to the service entrance, and shall notify the appropriate utility company.
(c) Additional inspections or inspection trips made by the city plumbing inspector, made necessary through the failure of any plumbing contractor in charge of the work to specify location of the work or failure to install plumbing or apparatus in proper manner, or to otherwise create conditions making such additional inspections or trips necessary, are hereby designated extra plumbing inspections. For each such extra plumbing inspection, the following fees shall apply:
Re-inspection - 1st | $30.00
2nd | $60.00
3rd | $90.00
4th | $100.00
All fees are to be paid by the contractor into the treasury of the city. Under no circumstances shall any fees be paid directly to the inspector.
(d) Nothing in this section shall be construed to require extra fees for the several inspections made necessary in the regular order of plumbing construction work.
(e) A certificate of approval may be issued authorizing the connection and use of temporary work. Such certificate shall be issued to expire at a time to be stated therein and shall be revocable by the plumbing inspector for cause.
(f) A preliminary certificate of approval may be issued authorizing the connection and use of certain specific portions of an in completed installation. Such certificate shall be revocable at the discretion of the plumbing inspector.
(g) When any part of a installation is to be hidden from view by the permanent placement of the parts of the building, the contractor shall notify the plumbing inspector and such parts of the installations shall not be concealed until they have been inspected and approved by the plumbing inspector. On large installations, where the concealment of parts of the plumbing proceeds continuously, the contractor installing the plumbing shall give the plumbing inspector due notice and inspections shall be made periodically during the progress of the work. If, upon inspection, any installation is not found to be fully in conformity with the provisions of this article, the plumbing inspector shall at once forward the person making the installation a written notice stating the defects which have been found to exist.
(Ord. No. 2199, § 2, 3-6-12)
Source: City of Biloxi, Mississippi, Code of Ordinances and Land Development Ordinance (Municode Library, library.municode.com)URL: https://library.municode.com/ms/biloxi/codes/code_of_ordinances?nodeId=COOR_CH5BU_ARTVPL_S5-5-13INCEAPFetched: 11/1/2026