Discharge permits.
Round Rock Code of Ordinances § 44-84
in effectSec. 44-84. - Discharge permits.
(a) Applicability. The following shall obtain a discharge permit:
(1) Significant users;
(2) Categorical users;
(3) Businesses or industries with a manufacturing process;
(4) Any other business, individual or entity connected to the sanitary sewer, which in the opinion of the control authority requires a permit.
These entities shall obtain a permit from the control authority prior to discharging non-domestic sewage to the BCRWWS. Permit applications shall be submitted to the control authority prior to permit issuance. Either the owner or operator of a user's facility shall submit the application.
(b) Denial or condition of permit. The control authority has the right to deny or condition a permit for any nondomestic discharges that do not meet the pretreatment requirements or would cause the city to be noncompliant with the conditions of the BCRWWS's discharge permits.
(c) Permit conditions.
(1) Minimum conditions. The permit will contain the following minimum conditions:
a. Period during which the permit is effective, in no case greater than five years. A statement that indicates the wastewater discharge permit issuance date, expiration date and effective date is required;
b. Transferability of the permit to a new owner or operator allowable only with notification and approval of control authority;
c. Limits on the volume and quality of sewage discharged based on the pretreatment standards;
d. Self-monitoring, sampling, reporting, notification, and record-keeping requirements. These requirements shall include an identification of pollutants (or BMPs) to be monitored, sampling location, sampling frequency, and sample type based on federal, state and local law;
e. A statement of applicable civil and criminal penalties for violation of pretreatment standards and requirement, and any other applicable compliance schedule. Such schedules may not extend the compliance date beyond applicable federal deadlines;
f. Effluent limits, including BMPs, based on applicable pretreatment standards; and
g. Requirements to control slug discharge, if determined by the control authority to be necessary.
(2) Other conditions. The following conditions, as applicable, shall be in the permit:
a. Conditions and compliance schedule necessary to achieve compliance with the pretreatment requirements;
b. Plans to prevent and control spills and batch discharges;
c. Any other conditions necessary to ensure compliance with the pretreatment requirements, and other federal, state and local requirements; and
d. A statement requiring that all reports contain the certification statement at 40 CFR 403.6(a)(2);
e. Limits on the average and/or maximum rate of discharge, time of discharge, and/or requirements for flow regulation and equalization;
f. Requirements for the installation of pretreatment technology, pollution control, or construction of appropriate containment devices, designed to reduce, eliminate, or prevent the introduction of pollutants into the treatment works;
g. Requirements for the development and implementation of spill control plans or other special conditions including best management practices necessary to adequately prevent accidental, unanticipated, or non-routine discharges;
h. Development and implementation of waste minimization plans to reduce the amount of pollutants discharged to the POTW;
i. Requirements for installation and maintenance of inspection and sampling facilities and equipment, including flow measurement devices;
j. A statement that compliance with the individual wastewater discharge permit does not relieve the permittee of responsibility for compliance with all applicable federal and state pretreatment standards, including those which become effective during the term of the individual wastewater discharge permit.
(d) Permit application.
(1) Applications for new permits, permit renewals, and permit modifications shall be made on a standard form provided by the control authority. Applications shall be submitted to the control authority.
(2) Incomplete or inaccurate applications will not be processed and will be returned to the user for revision.
(e) Existing users. Significant users with existing nondomestic discharges prior to March 14, 1990, shall submit a permit application before September 15, 1990. Other users with existing nondomestic discharges prior to March 14, 1990, shall submit a permit application before June 15, 1990. Existing users shall be allowed to discharge nondomestic sewage without a permit until the control authority has issued the user a permit, if the user has submitted a permit application with the applicable time period.
(f) New users. A new user shall submit a permit application and obtain a permit before discharging to the POTW. An application shall be submitted by significant users at least 180 days before the date the discharge will begin or recommence. It is recommended that an application be submitted by other user at least 90 days before the date the discharge will begin or recommence
(g) Discharge and permit modifications. If a user with a discharge permit wishes to add or change a process or operation which would change the nature or increase the quantities of materials discharged to the POTW such that the user would be noncompliant with the user's permit requirements or the pretreatment requirements, the user shall obtain approval by the control authority prior to making these additions or changes to the discharge. Approval shall be given by the control authority by a modification, or revocation and re-issuance of the permit. A significant user shall submit an application for permit modification at least 180 days before the date the change in discharge is expected to begin. It is recommended that an application be submitted by other users at least 90 days before the date the change in discharge is expected to begin.
(h) Permit renewal. A permit may have a period of duration up to five years. A permit shall be renewed by submitting an application for renewal. An application for the user shall be submitted at least 90 days before the expiration date of the existing permit.
(i) Re-opening of permit. The control authority may modify an individual wastewater discharge permit for good cause, including, but not limited to:
(1) To incorporate any new or revised federal, state, or local pretreatment standards or requirements;
(2) To address significant alterations or additions to the user's operation, processes, or wastewater volume or character since the time of the individual wastewater discharge permit issuance;
(3) A change in the POTW that requires either a temporary or permanent reduction or elimination of the authorized discharge;
(4) Information indicating that the permitted discharge poses a threat to the POTW, personnel, or the receiving waters;
(5) Violation of any terms or conditions of the individual wastewater discharge permit;
(6) Misrepresentation or failure to fully disclose all relevant facts in the wastewater discharge permit application or in any required reporting;
(7) Revision or a grant of variance from categorical pretreatment standards pursuant to 40 CFR 403.13;
(8) To correct typographical or other errors in the individual wastewater discharge permit; or
(9) To reflect a transfer of the facility ownership or operation to a new owner or operator where requested in accordance with subsection 44-84(j).
(j) Changes in owner or operator.
(1) Transfer of permit. A permit shall only be transferred to a new owner or operator if the following conditions are met. The expiration date of the permit is not extended by the transfer. The control authority will send to the owner or operator a revision to the permit to reflect the change in owner or operator.
a. The nature of the discharge or operation of the facility will not change under the new owner or operator;
b. The current owner or operator notifies the control authority at least 30 days in advance of the proposed transfer date;
c. The notification includes a written agreement between the current and new owner or operator continuing a specific date for transfer of permit responsibility, coverage, and liability between them; and
d. The control authority does not notify the current and new owner or operator of the control authority's intent to revoke and reissue the permit. If the control authority does not notify, the transfer is effective on the date specified in the written agreement.
(2) Revocation and re-issuance of permit. If above conditions in subsection (j)(1) of this section are not met, the control authority shall require the new owner or operator to submit a permit application as a new user and obtain a permit before discharging to the POTW. In addition, the current owner or operator shall notify the control authority at least 30 days in advance of the proposed date on which the ownership will change.
(3) Advance notice. Failure to provide advance notice of a transfer renders the individual wastewater discharge permit void as of the date of the facility transfer.
(k) Wastewater discharge permit revocation.
(1) The control authority may revoke an individual wastewater permit for good cause, including but not limited to, the following reasons:
a. Failure to notify the control authority of significant changes to the wastewater prior to the changed discharge;
b. Failure to provide prior notification to the control authority of changed conditions pursuant to this article;
c. Misrepresentation of failure to fully disclose all relevant acts in the wastewater discharge permit application;
d. Falsifying self-monitoring reports and certification statements;
e. Tampering with monitoring equipment;
f. Refusing to allow the control authority timely access to the facility premises and records;
g. Failure to meet effluent limitations;
h. Failure to pay fines;
i. Failure to pay sewer charges;
j. Failure to meet compliance schedules;
k. Failure to complete a wastewater survey or wastewater discharge permit application;
l. Failure to provide advance notice of transfer of business ownership of a permitted facility; or
m. Violation of any pretreatment standard or requirement, or any terms of the wastewater discharge permit or this article.
(2) All wastewater discharge permits issued to a user are void upon the issuance of a new individual wastewater discharge permit to that user.
(l) Application signatories and certifications.
(1) All wastewater discharge permit applications, user reports and certification statements must be signed by an authorized representative of the user and contain the certification statement of this article.
(2) If the designation of an authorized representative is no longer accurate because a different individual or position has responsibility for the overall operation of the facility or overall responsibility for environmental matters for the company, a new written authorization satisfying the requirements of this section must be submitted to the control authority prior to or together with any reports to be signed by an authorized representative.
(m) Regulation of waste received from other jurisdictions.
(1) If another municipality, or user located within another municipality, contributes wastewater to the POTW, the control authority shall enter into an intermunicipal agreement with the contributing municipality.
(2) Prior to entering into an agreement required by subsection (m)(1), above, the control authority shall request the following information from the contributing municipality:
a. A description of the quality and volume of wastewater discharged to the POTW by the contributing municipality;
b. An inventory of all users located within the contributing municipality that are discharging to the POTW; and
c. Such other information as the control authority may deem necessary.
(3) An intermunicipal agreement, as required by subsection (m)(1), above, shall contain the following conditions:
a. A requirement for the contributing municipality to adopt a sewer use ordinance or similar control document, that is at least as stringent as the control authority's ordinance. The document must include local limits, BMRs, and a requirement that the control document and limits must be revised as necessary to reflect changes made to the control authority's ordinance or local limits;
b. A requirement for the contributing municipality to submit a revised user inventory on at least an annual basis;
c. A provision specifying which pretreatment implementation activities, including individual wastewater discharge permit issuance, inspection and sampling, and enforcement, will be conducted by the contributing municipality; which of these activities will be conducted by the control authority; and which of these activities will be conducted jointly by the contributing municipality and the control authority;
d. A requirement for the contributing municipality to provide the control authority with access to all information that the contributing municipality obtains as part of its pretreatment activities;
e. Limits on the nature, quality, and volume of the contributing municipality's wastewater at the point where it discharges to the POTW;
f. Requirements for monitoring the contributing municipality's discharge;
g. A provision ensuring the control authority access to the facilities of users located within the contributing municipality's jurisdictional boundaries for the purpose of inspection, sampling, and any other duties deemed necessary by the control authority; and
h. A provision specifying remedies available for breach of the terms of the intermunicipal agreement.
(Code 1995, § 10.405; Ord. No. O-2020-0222, §§ I, II, 8-13-2020)
Source: City of Round Rock, Texas, Code of Ordinances (Municode Library, library.municode.com)URL: https://library.municode.com/tx/round_rock/codes/code_of_ordinances?nodeId=PTIICOOR_CH44UT_ARTIVPRPR_S44-84DIPEFetched: 11/16/2026