Prequalification of construction bidders.
Richmond, Va., City Code § 21-46
in effectSec. 21-46. - Prequalification of construction bidders.
(a) Any prequalification of prospective contractors for construction shall be pursuant to a prequalification process consistent with this section. The opportunity to prequalify shall be given to any prospective bidder who has not been suspended or debarred under this chapter.
(b) Good faith minority business enterprise and emerging small business participation efforts previously made and those efforts proposed to be made by the prospective bidder shall be information required to prequalify. In the absence of different weights or criteria established by the Office of Minority Business Development, a prospective bidder's good faith minority business enterprise and emerging small business participation efforts shall comprise 30 percent of the total prequalification score. The Office of Minority Business Development shall develop forms and criteria for and shall assess a bidder's prequalification with respect to past and proposed minority business enterprise and emerging small business participation efforts. No prospective bidder receiving less than 50 percent of the possible minority business enterprise and emerging small business participation efforts percentage points shall be prequalified unless granted a waiver by the Chief Administrative Officer. The Chief Administrative Officer may allow a waiver only when:
(1) No other qualified, willing, and able prospective bidders have applied for prequalification; and
(2) The Director of the Office of Minority Business Development certifies that the prospective bidder is unable due to circumstances beyond its control to make good faith minority business enterprise and emerging small business participation efforts that would achieve a higher number of percentage points. The proposed efforts must be set forth in detail in writing and must be legally binding on the prospective bidder.
(c) The Office of Minority Business Development shall maintain and update a list of bona fide minority business enterprises and emerging small businesses that are engaged in various fields of construction subcontracting and shall make this list available to all prospective prime construction contractors who desire to use it for assistance in attaining the highest possible ranking for good faith minority business enterprise and emerging small business participation efforts.
(d) The application form used in the prequalification process shall set forth the criteria upon which the qualifications of prospective contractors will be evaluated. The application form shall request of prospective contractors only such information as is appropriate for an objective evaluation of all prospective contractors pursuant to such criteria. Such form shall allow the prospective contractor seeking prequalification to request, by checking the appropriate box, that all information voluntarily submitted by the contractor pursuant to this subsection shall be considered a trade secret or proprietary information subject to Section 21-5(f).
(e) Advance notice shall be given of the deadline for the submission of prequalification applications. The deadline for submission shall be sufficiently in advance of the date set for the submission of bids as to allow the procedures set forth in this subsection to be accomplished.
(f) At least 30 calendar days prior to the date established for submission of bids or proposals under the procurement of the contract for which the prequalification applies, the City shall advise in writing each contractor which submitted an application whether that contractor has been prequalified. If a contractor is denied prequalification, the written notification to such contractor shall state the reasons for such denial of prequalification and the factual basis of such reasons. A decision by the City denying prequalification under this section shall be final and conclusive unless the contractor appeals the decision as provided in Section 21-161.
(g) Prequalification may be denied to any contractor only if the City finds one of the following:
(1) The contractor does not have sufficient financial ability to perform the contract that would result from such procurement. If a bond is required to ensure performance of a contract, evidence that the contractor can acquire a surety bond from a corporation included on the United States Treasury list of acceptable surety corporations in the amount and type required by the City shall be sufficient to establish the financial ability of such contractor to perform the contract resulting from such procurement;
(2) The contractor does not have appropriate experience to perform the construction project in question;
(3) The contractor or any officer, director or owner thereof has had judgments entered against the contractor within the past ten years for the breach of contracts for governmental or nongovernmental construction, including, but not limited to, design-build or construction management;
(4) The contractor has been in substantial noncompliance with the terms and conditions of prior construction contracts with the City without good cause. If the City has not contracted with a contractor in any prior construction contracts, the City may deny prequalification if the contractor has been in substantial noncompliance with the terms and conditions of comparable construction contracts with another public body without good cause. The City may not utilize this subsection to deny prequalification unless the facts underlying such substantial noncompliance were documented in writing in the prior construction project file and such information relating thereto was given to the contractor at that time, with the opportunity to respond;
(5) The contractor or any officer, director, owner, project manager, procurement manager or chief financial official thereof has been convicted within the past ten years of a crime related to governmental or nongovernmental construction or contracting, including, but not limited to, a violation of:
a. Article VIII of this chapter;
b. The Virginia Governmental Frauds Act, Code of Virginia, § 18.2-498.1 et seq.;
c. Code of Virginia, Title 59.1, Ch. 4.2 (Code of Virginia, § 59.1-68.6 et seq.), which pertains to conspiracy to rig bids to government; or
d. Any substantially similar law of the United States or another state;
(6) The contractor or any officer, director or owner thereof is currently debarred pursuant to an established debarment procedure from bidding or contracting by any public body, agency of another state or agency of the Federal government;
(7) The contractor failed to provide to the City in a timely manner any information requested by the City relevant to Subsections (g)(1) through (6) of this section; and
(8) The contractor failed to make or propose to make good faith minority business enterprise and emerging small business participation efforts as set forth in Subsection (b) of this section. A contractor that fails to receive a score of at least 50 percent of the possible minority business enterprise and emerging small business participation efforts percentage points shall not be prequalified to bid on or receive the contract.
(Code 1993, § 22.1-41.1; Code 2004, § 74-50; Code 2015, § 21-46; Code 2020, § 21-46; Ord. No. 2004-360-330, § 1, 12-13-2004; Ord. No. 2006-134-105, § 1, 5-8-2006)
Source: City of Richmond, Virginia, Code (2026 recodification) and Charter (Municode Library, library.municode.com)URL: https://library.municode.com/va/richmond/codes/code_of_ordinances?nodeId=PTIICICO_CH21PUPR_ARTIICOFOMESOSE_S21-46PRCOBIFetched: 11/8/2026