14.16.040 - Standard refunding.
A. Standard refunding agreements.
1. The city may enter into an agreement which provides for repayment of a portion of the cost of the main extension lying between the original point of supply and the customer's property from main frontage fees collected from other properties frontage to the main extension covered by such agreement during the term provided in the agreement or until the amount advanced by the customer has been satisfied, as determined in accordance with the provisions of this title and/or the department's service rules.
2. The following items may be eligible for standard refunding:
a. Water, sewer, and reclaimed water main extensions to a project;
b. Water, sewer, and reclaimed water main extensions adjacent to a project; and/or
c. Water, sewer, and reclaimed water mains replacing existing mains.
3. The period during which refunds are due shall be 20 years, commencing on the date when the infrastructure covered by the agreement is completed, tested, and accepted by the city.
4. Construction shall be deemed to be complete when the utility infrastructure is constructed according to the approved plans and satisfies all applicable testing and acceptance criteria.
5. The city council shall grant the director the authority to enter into and execute any standard refunding agreement in which the city is not a participant. Should the city be a participant in a standard refunding agreement, such agreement must be approved according to city standard operating procedures and policies.
B. Standard refunding conditions.
1. Application for standard refunding agreement shall be submitted to the department in writing accompanied by documentation as required by the city from customer(s) constructing such infrastructure covered by the agreement. This application shall be submitted within 90 days of date of acceptance by the city of the infrastructure to be covered by such agreement.
2. All customers entering into any refunding agreement with the city shall pay all fees as outlined in this title and/or the department service rules. These fees are due and payable at the time of the execution of the agreement.
3. Customers may be eligible for a refund of main frontage fees collected by the city from other properties in accordance with this title.
4. All standard refunding calculations shall be rounded to the nearest foot and shall be assessed based on the frontage of the applicant's property, as indicated by the most current data in the Clark County assessor office records, adjacent to the right-of-way or easement where the existing water, sewer, or reclaimed water main is located in accordance with this title and/or the department's service rules.
5. After execution of a valid standard refunding agreement, all main frontage fees collected in accordance with this title and/or department service rules shall be paid within 60 days from the date of collection.
6. In the event any expense is incurred by the city within a period of one year after acceptance of the infrastructure installed by the customer covered by a standard refunding agreement due to defective materials or workmanship the amount of such expense shall be deducted from any refund(s) that may become due to the customer thereafter.
(Ord. 2536, § 87, 2006)