San José Municipal Code § 4.10.150 Causes.
4.10.150 - Causes.
The Debarring Official can debar a Contractor for any of the following causes.
A. The Contractor submitted to the City of false, untrue or misleading information in any context, including, without limitation, the procurement or performance of a Contract. This cause includes, without limitation, each of the following:
1. The submission of false, untrue or misleading information based on the Contractor acting in deliberate ignorance, or in reckless disregard, of the truthfulness of the information,
2. The submission of false, untrue or misleading information that the Contractor represents as accurate information without having taken reasonable steps of determine the accuracy of the information, or
3. The failure to disclose and correct an inadvertent submission of false, untrue or misleading information after discovering the information is false, untrue or misleading.
B. The Contractor submitted a false claim as defined in any applicable federal, state, or municipal false claims law.
C. The Contractor committed an act indicating a lack of business integrity or honesty, including, without limitation, fraud, bribery, collusion, bid rigging, price fixing, perjury, lying, embezzlement, theft, forgery, or falsification or destruction of records or evidence.
D. The Contractor failed to comply with, or disregarded, the terms and conditions of a Contract.
E. The Contractor's performance on a Contract was substandard, including, without limitation, substandard quality of work, repeated unexcused delays, or repeated failure to cooperate with the City department administering the Contract.
F. The Contractor violated federal, state, County of Santa Clara, or City law, administrative regulation, order, or official policy applicable to the performance of the Contract or the procurement of the Contract. This includes, without limitation, each of the following:
1. Noncompliance with requirements that protect the integrity of the procurement process,
2. Noncompliance with labor or safety requirements such as prevailing wage, living wage, wage theft prevention, occupational safety and health, and nondiscrimination requirements,
3. Noncompliance with requirements for the handling, transfer, storage or disposal of hazardous materials or hazardous waste, or
4. Noncompliance with conflict of interest requirements, such as the City's gift ordinance set forth in Chapter 12.08.
G. The Contractor engaged in conduct resulting in debarment by any other federal, state or local agency.
H. The Contractor knowingly used a debarred person or entity to perform any part of a Contract.
I. The Contractor breached its duty of good faith and fair dealing to the City, including, without limitation, the filing of nonmeritorious claims or lawsuits against any public agency or agencies.
J. The Contractor lacks financial responsibility.
K. Any conviction, verdict, judgment, settlement, stipulation, or plea agreement based on any of the above-referenced causes for Debarment.
L. Any other cause of such a serious or compelling nature that it demonstrates the Contractor's present lack of responsibility.
(Ord. 30733.)