Sec. 10-29. - Mitigation of other adverse effects.
(a) The applicant bears the burden of proving no material weakening or damage of dunes. If the concurrent beach/dune committee finds that no material weakening of dunes or material damage to dunes will occur, as demonstrated by the applicant, the committee shall then determine whether any adverse effects will result from the activity. If the committee finds there will be adverse effects on dunes or dune vegetation seaward of the dune protection line or in critical dune areas, the committee may issue a permit only if the applicant demonstrates that adverse effects can be mitigated as required by the mitigation sequence. If the committee issues a permit, it shall include appropriate permit conditions incorporating the requirements of this article.
(b) The mitigation sequence consists of the following requirements.
(1) Avoidance.
a. Avoidance means avoiding adverse effects altogether by not taking a certain action or parts of an action. A permit shall not be issued allowing any adverse effects on dunes or dune vegetation seaward of the dune protection line unless the applicant proves there is no practicable alternative to the proposed activity, proposed site, or proposed methods for conducting the activity, and the activity will not materially weaken the dunes or dune vegetation. The permittee shall include information as to practicable alternatives in the permit application.
b. To avoid adverse effects on dunes and dune vegetation seaward of the dune protection line as required by subsection (b)(1)a. of this subsection, permittees shall not:
1. Construct pipelines, except those that are exempt, seaward of the dune protection line unless there is no practicable alternative;
2. Engage in any construction unless it is located as far landward of dunes as practicable, except construction providing access to and from a public beach;
3. Construct any road parallel to the beach within two hundred (200) feet landward of the vegetation line, nor construct any other road parallel to the beach unless it is located as far landward of dunes as practicable;
4. Construct new artificial channels, including stormwater runoff channels, unless there is no practicable alternative; or
5. Cause any such adverse effects for which the concurrent beach/dune committee determines there is a practicable alternative that would avoid such adverse effects.
(2) Minimization.
a. Minimization means minimizing effects on dunes and dune vegetation by limiting the degree or magnitude of the action and its implementation. Permittees shall minimize adverse impacts to dunes and dune vegetation by limiting the degree or magnitude of the action and its implementation. If the concurrent beach/dune committee determines that adverse effects on dunes or dune vegetation seaward of the dune protection line cannot be avoided, it may issue a permit allowing the proposed alteration, provided that the permit contains a condition requiring the permittee to minimize such adverse effects to the greatest extent practicable.
b. To minimize unavoidable adverse effects as required by subsection (b)(2)a. of this section, permittees shall:
1. Locate nonexempt pipelines across previously disturbed areas, such as blowout areas, and minimize disturbance of dune surfaces where use of previously disturbed areas is not practicable;
2. Minimize construction and pedestrian traffic on or across dune areas to the greatest extent practicable, accounting for trends of dune movement and beach erosion in that area;
3. Route all pedestrian access to and from beaches through washover areas or over elevated walkways, and conspicuously mark all such access that is public with permanent signs so indicating;
4. Minimize the number of private access ways from any proposed subdivision, multiple dwelling, or commercial facility. In some cases, the minimum beach access may be only one (1) access way. In determining the appropriate grouping of access ways, the concurrent beach/dune committee shall consider the size and scope of the development;
5. Post signs in areas where pedestrian traffic is high explaining the functions of dunes and the importance of vegetation in preserving dunes;
6. Where practicable, provide vehicular access to and from beaches by using existing roads or from roads constructed in accordance with subsection (b)(1)b.3. of this section, unless public beach access is restricted, and where possible, improve existing access roads with elevated berms near the beach that prevent channelization of floodwaters;
7. Where practicable, locate new beach access roads in washover areas, blowout areas or other areas where dune vegetation has already been disturbed, construct such roads along the natural land contours, and minimize their width;
8. Where practicable, locate new beach access roads at an oblique angle to the prevailing wind direction;
9. Prohibit persons from using or parking any motor vehicle on, through, or across dunes outside designated access ways;
10. Maximize use of natural or existing drainage patterns when providing for stormwater runoff and retention; and
11. Locate and construct new artificial stormwater runoff channels and retention basins so as to avoid erosion and unnecessary construction of additional channels and to direct all runoff inland and not to the Gulf of Mexico through dune areas.
(3) Mitigation.
a. Mitigation means repairing, rehabilitating, or restoring affected dunes and dune vegetation. Where adverse effects on dunes and dune vegetation can not be avoided or minimized, the concurrent beach/dune committee shall set appropriate permit conditions requiring that permittees repair, rehabilitate, or restore affected dunes to the same volume as the pre-existing dunes and dune vegetation so that affected dunes will be superior or equal to the pre-existing dunes in their ability to protect adjacent public and private property from potential flood damage, nuisance, and erosion and to protect natural resources. The committee shall consider the comments of the general land office, federal and state natural resource agencies, and dune vegetation experts in determining the appropriate mitigation method.
b. Permittees may mitigate adverse effects on dunes using vegetative or mechanical means. Permittees shall:
1. Restore dunes to approximate the naturally formed dune position or location, contour, volume, elevation, vegetative cover, and sediment content in the area;
2. Allow for the natural dynamics and migration of dunes;
3. Use discontinuous or continuous temporary sand fences or a concurrent beach/dune committee approved method of dune restoration, where appropriate, considering the characteristics of the site; and
4. Restore or repair dunes using indigenous vegetation that will achieve the same protective capability as or greater capability than the surrounding natural dunes.
c. In authorizing or requiring restoration of dunes, the concurrent beach/dune committee shall give priority to stabilization of blowouts and breaches. Before permitting stabilization of washover areas, the committee shall:
1. Assess the overall impact of the project on the beach/dune system;
2. Consider any adverse effects on hydrology and drainage which will result from the project; and
3. Require that equal or better public beach access be provided to compensate for impairment of any public beach access previously provided by the washover area.
(4) Compensation.
a. Compensation means compensating for effects on dunes and dune vegetation by replacing or providing substitute dunes and dune vegetation. Compensation consists of replacement of the affected dunes or dune vegetation on the site where the dunes and dune vegetation were originally located. The concurrent beach/dune committee shall set appropriate permit conditions requiring permittees to compensate for all adverse effects on dunes and dune vegetation that can not be avoided, minimized, or otherwise mitigated. In setting appropriate conditions, the committee shall consider the recommendations of the general land office, federal and state natural resource agencies, and dune vegetation experts. Preference shall be given to stabilization of blowouts and breaches.
b. Permittees shall follow the requirements of subsections (3)b.—c. and (4)e.3.—5. of this subsection when replacing dunes or dune vegetation.
c. On-site compensation consists of replacement of the affected dunes or dune vegetation on the site where the dunes and dune vegetation were originally located. Permittees shall locate compensation efforts on the construction site, where practicable.
d. A permittee may locate compensation efforts off the construction site if the permittee demonstrates that:
1. On-site compensation is not practicable;
2. The off-site compensation will be located as close to the construction site as practicable;
3. The off-site compensation has achieved a 1:1 ratio of proposed adverse effects on successful, completed, and stabilized restoration prior to beginning construction; and
4. The permittee has notified FEMA, Region 6, of the proposed off-site compensation.
e. Permittees shall provide the following information when proposing off-site compensation:
1. The name, address, phone number, and fax number, if applicable, of the owner of the property where the off-site compensation will be located;
2. A legal description of property intended to be used for the proposed off-site compensation;
3. The source of the sand and dune vegetation to be used;
4. All information regarding permits and certificates issued for the restoration of dunes and dune vegetation on the compensation site;
5. All relevant information regarding the success, current status, and stabilization of the dune restoration efforts on the compensation site;
6. Any increase in potential flood damage to the site where the adverse effects on dunes and dune vegetation will occur and to the public and private property adjacent to that site; and
7. The proposed date of initiation of the compensation.
f. Permittees shall compensate for adverse effects on dune vegetation by planting indigenous vegetation on the affected dunes. Permittees may not remove existing vegetation from property not owned by the permittee unless the permittee includes in the permit application written permission from the property owner. The permit application must identify the source of any sand and vegetation which will be used in compensation.
g. Permittees shall begin compensation prior to or concurrently with the commencement of construction. If compensation is not to be completed prior to commencement of construction, the permittee shall provide proof of financial responsibility in an amount necessary to complete the compensation, in the form of an irrevocable letter of credit, performance bond, or any other instrument acceptable to the city.
h. Permittees shall notify the department in writing of the actual date of initiation within ten (10) working days after compensation is initiated. If the permittee fails to begin compensation on the date proposed in the application, the permittee shall state the reason for the delay. The concurrent beach/dune committee shall take this reason into account when determining whether a permittee has violated the compensation deadline.
i. Permittees shall conduct compensation efforts continuously until the repaired, rehabilitated, and restored dunes and dune vegetation are equal or superior to the pre-existing dunes and dune vegetation. These efforts shall include preservation and maintenance pending completion of compensation.
j. A compensation project is deemed complete when the position, contour, volume, elevation, and vegetative cover of the restored dunes are equal or superior to the pre-existing dunes and dune vegetation.
k. The planning director shall provide written notification to the general land office upon determining that the compensation is complete. If the planning director does not receive an objection from the general land office regarding the completion of compensation within thirty (30) days after the general land office is notified in writing, the planning director may certify to the permittee that the compensation is complete.
l. The permittee shall be deemed to have failed to achieve compensation if a 1:1 ratio has not been achieved within three (3) years after the beginning of compensation efforts.
(Ord. No. 22164, §§ 1, 2, 2-28-1995; Ord. No. 24777, § 5, 2-19-2002; Ord. No. 25260, § 11, 4-15-2003)