Cost or pricing data.
Atlanta City Code § 2-1201
in effectSec. 2-1201. - Cost or pricing data.
(a) Submissions relating to award of contracts.
(1) Required. A prospective contractor shall submit cost or pricing data when the contract is expected to exceed $20,000.00 and is to be awarded under sections 2-1189, 2-1191 or 2-1193.
(2) Exceptions. The submission of cost or pricing data relating to the award of a contract is not required when:
a. The contract price is based on adequate price competition as determined by the chief procurement officer;
b. The contract price is set by law or regulation; or
c. It is determined in writing by the chief procurement officer that the requirements of subsection (a)(1) of this section may be waived and
(b) Submissions relating to change orders or contract modifications.
(1) Required. A contractor shall submit cost or pricing data prior to the pricing of any change order or contract modification, including adjustments to contracts awarded by competitive sealed bidding, whether or not cost or pricing data was required in connection with the initial solicitation, when the modification involves increases that are expected to exceed $20,000.00.
(2) Exceptions. The submission of cost or pricing data relating to the pricing of a change order or contract modification is not required when:
a. Unrelated and separately priced adjustments for which cost or pricing data would not be required are consolidated for administrative convenience; or
b. It is determined in writing by the chief procurement officer that the requirements of subsection (b)(1) of this section may be waived and the determination states the reasons for such waiver.
(c) Verification required. A contractor required to submit cost or pricing data in accordance with this section shall verify that, to the best of the contractor's knowledge and belief, the cost or pricing data submitted was accurate, complete and current as of the date it was submitted.
(d) Price adjustment provision required. Any contract award, change order or contract modification under which the submission and verification of cost or pricing data are required shall contain a provision stating that the price to the city, including a profit or fee, shall be adjusted to exclude any costs found by the city to have been increased because the contractor furnished cost or pricing data was inaccurate, incomplete or not current as of the date it was submitted.
(Ord. No. 2009-78(09-O-1876), § 4, 12-15-09)
Source: City of Atlanta, Code of Ordinances (Charter and Related Laws, General Ordinances, Land Development Code) (Municode Library, library.municode.com)URL: https://library.municode.com/ga/atlanta/codes/code_of_ordinances?nodeId=PTIICOORENOR_CH2AD_ARTXPRREESCO_DIV4SOSECOFO_S2-1201COPRDAFetched: 10/28/2026