Right-of-way patching and restoration.
Minneapolis Code of Ordinances § 430.70
in effect430.70. - Right-of-way patching and restoration.
The work to be done under the excavation permit, and the patching and restoration of the right-of-way as required herein, must be completed within the dates specified in the permit, increased by as many days as work could not be done because of circumstances beyond the control of permittee or when work was prohibited as unseasonable or unreasonable under this chapter. In addition to patching its own work, the permittee must restore the general area of the work, and the surrounding areas, including the paving and its foundations, to the same condition that existed before the commencement of the work. The permittee must ensure compliance with this section by inspecting the area of the work before commencement and following completion of all work performed under the permit.
In its application for an excavation permit, the permittee may indicate a preference either to have the city restore the right-of-way or to restore the right-of-way itself. The city retains the right of first refusal for all or any portion of restoration work within the right-of-way.
(1) City restoration. If the city restores all or any portion of the right-of-way, permittee shall pay the costs thereof within thirty (30) days of billing.
(2) Permittee restoration. If the city foregoes its right of first refusal under this section and the permittee restores all or any portion of the right-of-way itself permittee shall at the time of application of an excavation permit post construction security. If, following such restoration by permittee, the pavement settles due to defective work, the permittee shall pay to the city, within thirty (30) days of billing, all costs associated with correcting the defective work.
When performing any work in the right-of-way, the permittee shall act according to the standards of and shall utilize the materials specified by the city engineer. The city engineer shall have the authority to prescribe the manner and extent of the restoration, and may do so in written procedures of general application or on a case-by-case basis. The city engineer in exercising this authority shall be guided by Minnesota Rule 7819.1100 when applicable.
Methods of restoration may include, but are not limited to, patching, replacement of the right-of-way base, and milling and overlay of the entire area of the right-of-way affected by the work.
The permittee shall correct defects in patching or restoration performed by the permittee or its agents upon notification from the city engineer, and correct all restoration work to the extent necessary using the method required by the city engineer. Said work shall be completed within five (5) calendar days of the receipt of the notice from the city engineer, not including days during which work cannot be done because of circumstances constituting force majeure or days when work was prohibited as unseasonable or unreasonable pursuant to Chapter 429 and 430.
If the permittee fails to restore the right-of-way in the manner and to the condition required by the city engineer, or fails to satisfactorily and timely complete all restorations required by the city engineer, the city engineer, at his or her option, may do such work at the expense of permittee and/or the city engineer may pursue collection of any construction security required under this chapter.
In lieu of right-of-way restoration the city engineer may impose a degradation fee. However, the right-of-way user shall remain responsible for patching, and the degradation fee shall not include the cost to accomplish these responsibilities. (96-Or-127, § 1, 11-22-96; 97-Or-069, § 4, 8-8-97; 2000-Or-026, § 6, 4-21-00; Ord. No. 2009-Or-022, § 3, 3-6-09)
Source: City of Minneapolis, Minnesota, Code of Ordinances, City Charter and Park and Recreation Board Code of Ordinances (Municode Library, library.municode.com)URL: https://library.municode.com/mn/minneapolis/codes/code_of_ordinances?nodeId=MICOOR_TIT17STSI_CH430RI-WPE_430.70RI-WPAREFetched: 11/2/2026