174.310. - Required generally.
(a) The fire marshal, before issuing, reviewing or processing any permit for the installation of any fire protection system, shall require the payment by the applicant for such permit of fees in the amounts herein provided. Further, no permit for the installation of any fire protection system shall be issued unless the applicant first files with the fire prevention bureau a complete set of plans for such system approved by the fire marshal.
(b) The valuation to be used in computing the permit and plan-check fees shall be the total contract cost of the proposed fire protection systems, including all associated equipment, materials and labor costs.
(c) Effective January 1, 2009, the fire protection systems permit fees shall be as follows:
Contract Cost (Rounded to nearest whole dollar) | Permit Fee
$1.00 to $1,200.00 | $65.00
$1,201.00 to $2,000.00 | $65.00 for the first $1,200.00 plus $4.37 for each additional $100.00 or fraction thereof
$2,001.00 to $25,000.00 | $99.94 for the first $2,000.00 plus $20.02 for each additional $1,000.00 or fraction thereof
$25,001.00 to $50,000.00 | $560.40 for the first $25,000.00 plus $14.44 for each additional $1,000.00 or fraction thereof
$50,001.00 to $100,000.00 | $921.48 for the first $50,000.00 plus $10.01 for each additional $1,000.00 or fraction thereof
$100,001.00 to $500,000.00 | $1,421.98 for the first $100,000.00 plus $8.01 for each additional $1,000.00 or fraction thereof
$500,001.00 to $1,000,000.00 | $4,625.18 for the first $500,000.00 plus $6.80 for each additional $1,000.00 or fraction thereof
$1,000,001.00 and up | $8,024.68 for the first $1,000,000.00 plus $5.36 for each additional $1,000.00 or fraction thereof
_____
(2005-Or-097, § 1, 10-21-05; 2008-Or-048, § 1, 6-20-08)