Commencement of excavation
HRS §269E-10
in effect269E-10. Commencement of excavation
The center shall not prohibit an excavator from beginning excavation work:
(1) After receiving notice that all affected
operators have fulfilled the requirements of section 269E-9; or
(2) Five working days after the excavator provides
notice of the excavation to the center pursuant to section 269E-7(a); provided
that this subsection shall not be construed as affording the excavator any
immunity or protection from claims for damages or injuries relating to the
excavation.
[L 2004, c 141, pt of §1, §7; am L 2009, c 72, §3]
Source: Hawaii State Legislature (capitol.hawaii.gov), via Internet Archive capturesURL: http://www.capitol.hawaii.gov/hrscurrent/Vol05_Ch0261-0319/HRS0269E/HRS_0269E-0010.htmFetched: 11/10/2026