Appendix A. - Right-of-way network node design manual.
DIVISION I. GENERAL
a. Applicability.
The requirements of this design manual ("manual") shall apply to all installations in the right-of-way within the City of San Antonio consisting of equipment associated with network nodes, node support poles, and other poles on which network nodes and associated equipment are installed. The City of San Antonio shall not be responsible to applicants for such installations for the costs of compliance with this manual. The manual, however, is not intended to supersede or conflict with engineering, technical, or operational requirements found in CPS energy's pole attachment license agreements and pole attachment standards.
b. Sources of authority.
This manual is adopted pursuant to V.T.C.A., Local Government Code Ch. 284.
c. Definitions.
For purposes of this Manual, all terms herein shall be as defined in the City Code of San Antonio, including Chapters 29, 35 and 37, in Texas Local Government Code Chapter 284, or in this Manual.
1. "Antenna" means communications equipment that transmits or receives electromagnetic radio frequency signals used in the provision of wireless services.
2. "COSA" means the City of San Antonio, including all city departments, officers, officials, or employees authorized to act on city's behalf.
3. "CPS" means CPS Energy, the electric and gas municipally owned utility owned by COSA.
4. "Decorative pole" means a streetlight pole specially designed and placed for aesthetic purposes and on which no appurtenances or attachments, other than specially designed informational or directional signage or temporary holiday or special event attachments, have been placed or are permitted to be placed according to nondiscriminatory municipal codes.
5. "Design district" means an area that is zoned, or otherwise designated by municipal code, and for which the city maintains and enforces unique design and aesthetic standards on a uniform and nondiscriminatory basis.
6. "Historic district" means an area that is zoned or otherwise designated as a historic district under municipal, state, or federal law.
7. "HPO" means the City of San Antonio Historic Preservation Officer or their designee.
8. "Municipally owned utility pole" means a utility pole owned or operated by a municipally owned utility, as defined by Section 11.003, Texas Utilities Code, and located in a public right-of-way.
9. "Node support pole" means a pole installed by a network provider for the primary purpose of supporting a network node.
10. "OHP" means the City of San Antonio Office of Historic Preservation.
11. "Permit" means a written authorization for the use of the public right-of-way or collocation on a service pole required from a municipality before a network provider may perform an action or initiate, continue, or complete a project over which the municipality has police power authority.
12. "Pole" means a service pole, municipally owned utility pole, node support pole, or utility pole.
13. "ROW" means public street right-of-way within the jurisdiction of the City of San Antonio.
14. "Service pole" means a pole, other than a municipally owned utility pole, owned or operated by a municipality and located in a public right-of-way, including:
A. a pole that supports traffic control functions;
B. a structure for signage;
C. a pole that supports lighting, other than a decorative pole; and
D. a pole or similar structure owned or operated by a municipality and supporting only network nodes.
15. "Stealth" or "stealth design" means a method of camouflaging any network node, node support pole, or transport facility, including, but not limited to, supporting electrical or mechanical equipment, which is designed to enhance compatibility with adjacent land uses and be as visually unobtrusive as possible. Stealth design may include a repurposed structure.
16. "TCI" means the City of San Antonio Transportation and Capital Improvements Department.
17. "UDC" means the City of San Antonio Unified Development Code.
18. "UECM" means the Utility Excavation Criteria Manual Fourth Edition, as may be amended by city staff from time to time; available at http://www.sanantonio.gov/TCI/Services/Right-of-Way-and-Permits.
19. "Utility pole" means a pole that provides:
A. electric distribution with a voltage rating of not more than 34.5 kilovolts; or
B. services of a telecommunications provider, as defined by Section 51.002, Texas Utilities Code.
20. "Wireless service provider" means a person that provides wireless service to the public.
Unless noted otherwise, where the above definitions conflict with those found in Texas Local Government Code Chapter 284, the latter shall control.
DIVISION II. PROCEDURES
a. All installations of network nodes and related equipment in the City of San Antonio public ROW shall require a permit issued by TCI for the specific equipment and work actually installed and performed. Any said work performed without a permit shall be considered a violation of the San Antonio City Code and all persons or entities committing such violations may be subject to civil and criminal penalties as permitted by law.
b. Where the proposed installation of a network node or related equipment is to be on a Service Pole, applicants shall confirm site eligibility with TCI prior to submitting a permit application. Eligibility determinations shall be based on installation space availability, as well as public safety, technical, and other criteria consistent with applicable law and city policies.
c. To ensure the integrity of the traffic signal system and continued COSA compliance with federal and state laws, and the latest edition of the Texas Manual on Uniform Traffic Control Devices, (available at https://www.txdot.gov/government/enforcement/signage/tmutcd.html), TCI may deny access to Service Poles due to site operational conditions, limited space availability, public safety concerns, future traffic signal system planning, or other operational considerations. Eligibility approval for a particular location shall not be construed as eligibility approval for any other location.
d. Pursuant to Texas Local Government Code Section 284.104, written approval by the Director of TCI shall be required prior to the installation by a network provider of any new node support pole in a public ROW that is in a municipal park or is adjacent to a street or thoroughfare that is not more than fifty (50) feet wide and adjacent to single-family residential lots or other multifamily residences or undeveloped land designated for residential use by zoning or deed restrictions.
e. Pursuant to Texas Local Government Code Section 284.105, written approval by the Director of TCI shall be required prior to the installation by a network provider of any new node support pole in a public ROW that is in a Design District which requires the use of decorative poles, as listed in this Manual. Such approval shall require compliance with all applicable design and aesthetic standards described in this Manual.
f. Where a proposed installation is to be on a property or in a zoning district designated a Design District under this Manual, the applicant shall meet the city department with jurisdiction over the particular district for review of required and proposed installation aesthetics prior to submitting application materials for completeness review. Where a proposed installation is in more than one Design District, the applicant shall meet with OHP.
g. Where a proposed installation is to be on a property that is designated as a Historic Landmark, or is within a Historic, River Improvement Overlay, Viewshed Protection, or Mission Protection Overlay District, such installation shall be subject to review by OHP for compliance with this Manual, the Historic Design Guidelines and/or applicable Overlay District Guidelines, and the UDC, and the following additional procedures shall apply:
1. Prior to submitting a permit application, applicants shall meet with OHP to discuss potential equipment design modifications necessary to achieve compliance.
2. Applicants shall furnish OHP with accurate scaled drawings of all proposed new equipment, showing location relative to existing equipment, existing poles, and adjacent structures within five hundred (500) feet. Additional submittal materials for OHP review shall be per the instructions of the COSA Historic Preservation Officer.
h. Subject to director approval, applicants proposing service pole re-enforcement or replacement shall provide engineering design drawings and specifications demonstrating the proposed alteration to the pole.
i. The Chief Technology Officer, Right-of-Way Manager, HPO, or their designees may, at their discretion, require applicants make design modifications pursuant to Chapter 284, this or other COSA design manuals, and applicable regulatory or legal requirements. Such requested design modifications shall be a prerequisite to a determination that a permit application is complete.
j. No application review, or application review timeline under Texas Local Government Code Chapter 284, shall commence until an application is deemed complete by the Directors of TCI, ITSD, OHP or their designees.
k. ROW permit applicants shall submit complete structural calculations and drawings to TCI, sealed by a professional engineer licensed in the State of Texas, detailing anchorage, attachment, and support, including an industry standard pole load analysis certifying that the pole will safely support all applicable loads of all the existing and proposed equipment, facilities, and appurtenances.
l. Permit applications shall identify which Design Districts as defined in this Manual, if any, the proposed installation is within.
m. Permit applications shall clearly demonstrate compliance with the following, as applicable:
1. One (1) hour shutoff notice obligation;
2. Non-interference obligation;
3. Quick disconnect at node location;
4. Own power source, conduit, meter, and shutoff accessible by TCI; and,
5. Any applicable backhaul rights/rules.
n. Applications shall be evaluated on a case-by-case basis to ensure consideration of specific structural conditions, load capacities, visual and signal interference, aesthetics, and reservation of space for future COSA infrastructure.
o. Upon completion of installation work, applicants shall:
1. Provide the right-of-way manager with an affidavit of compliance, sealed by a professional engineer licensed in the State of Texas, certifying all work was carried out consistent with the previously submitted and approved calculations and drawings.
2. Upon completion of the installation, including a micro network node installation, applicant shall notify the director or designee, in writing and provide a picture of said installation, city right-of-way permit number if applicable, the GIS coordinates, date of installation, company site ID#, type of pole used for installation, pole owner, and description/type of installation, which will be included in the network node or node support pole site application records. The city will also require the applicant to label the installation with the city right-of-way permit number for easy reference and verification by city personnel.
A. Network provider shall maintain a current inventory of network node, including micro network node, and node support pole sites. Network provider shall provide to city a copy of the inventory of network node sites on an annual basis. The inventory of network node sites shall include city right-of-way permit number, GIS coordinates, date of installation, company site ID#, type of pole used for installation, pole owner, and description/type of installation for each network node installation. Concerning network node, micro network node, and node support pole sites that become inactive or never activated, the inventory of sites shall include the same information as active installations in addition to the date the site was deactivated and the date the node or node support pole was removed from the public right-of-way. City shall compare the inventory of sites to its records to identify any discrepancies. The inventory shall include network nodes installed on service poles, municipally owned utility poles and third-party proprietary poles. The annual inventory shall be due not later than September 30 of each year.
B. Any unauthorized network node, including micro network node, or node support pole sites that are identified by the city as a result of comparing the inventory of network node sites to internal records or through any other means may be subject to immediate removal. City shall provide written notice to network provider of any unauthorized site identified by city staff and applicant shall have thirty (30) days thereafter in which to submit a preexisting city right-of-way permit for said site. Failure to produce a city right-of-way permit or notification of installation corresponding with the unauthorized site will result in the imposition of an unauthorized installation charge, which shall be calculated by applying the SB1004 fee formula to the period spanning from the original date of installation of the unauthorized site to the date of the written notice sent by city. The total amount resulting from this calculation shall be assessed an interest rate of twelve (12) percent to constitute the applicable unauthorized installation charge. Thereafter, applicant shall submit a network node site application and applicable annual right-of-way rate for the unauthorized network node site.
DIVISION III. TECHNICAL REQUIREMENTS
a. General requirements.
1. In accordance with Texas Local Government Code Section 284.102, a network provider shall construct and maintain network nodes and node support poles described by Texas Local Government Code Section 284.101 in a manner that does not:
A. obstruct, impede, or hinder the usual travel or public safety on a public right-of-way;
B. obstruct the legal use of a public right-of-way by other utility providers;
C. violate nondiscriminatory applicable codes;
D. violate or conflict with the municipality's publicly disclosed public right-of-way design specifications; or
E. violate the federal Americans with Disabilities Act of 1990 (42 U.S.C. Section 12101 et seq.).
2. In addition to the foregoing, and in accordance with Texas Local Government Code Section 284.304, network nodes and node support poles described by Texas Local Government Code Section 284.101 shall be constructed and maintained in a manner that does not obstruct, interfere, or conflict with any public safety communication or traffic safety signal frequency.
3. In accordance with Texas Local Government Code Section 284.107, network providers shall comply with the City's nondiscriminatory undergrounding requirements in relation to an installation for which the City has approved a permit application, including municipal ordinances, zoning regulations, state law, private deed restrictions, and other public or private restrictions, that prohibit installing aboveground structures in a public right-of-way without first obtaining zoning or land use approval. This provision may not be interpreted to prohibit a network provider from replacing an existing structure.
b. Specific requirements.
In accordance with Texas Local Government Code Section 284.108, the following shall apply to all network node installations in the right of way ('ROW'):
1. All network nodes and related equipment shall be installed in accordance with chapter 29, article IV (COSA Right-of-Way Management Ordinance), and the UECM as applicable.
2. Network providers shall be responsible for ensuring compliance with all applicable federal, state, and other local installation and construction standards and industry best practices, as well as the Americans with Disabilities Act.
3. New node support poles shall be located at least two hundred and fifty (250) feet from any existing pole of any type, unless the director of TCI determines in his sole discretion that the network provider has shown good cause for granting an exception to the distance requirement. Good cause is determined in the director's sole discretion and, in any event must be based on the unavailability or unsuitability of all other feasible locations. Wireless antennas shall maintain a minimum ten (10) foot vertical and horizontal clearance from any electrical conductors including neutral conductors. Additional clearances may be required to ensure that field personnel are not exposed to unsafe radiation levels. Applicants are responsible for confirming applicable clearance requirements with CPS and COSA.
4. Electrical power to network nodes and related equipment shall be wholly separate from electrical power serving COSA equipment including traffic signal devices, street lighting, etc., unless otherwise authorized by the director or designee. In addition, applicants shall be responsible for compliance with applicable CPS meter requirements.
5. All electrical and communication cabling to network nodes and related equipment shall be run in its own conduit path outside of the conduit path used by COSA infrastructure, unless otherwise authorized by the director or designee.
6. In order to permit emergency power shut-downs, an electrical cutoff, accessible by TCI personnel, shall be provided at each network node or related equipment installation.
7. Installation of network nodes and related equipment shall not hinder the intended operation and visibility of all traffic control devices, including, but not limited to, signal faces, signals, detectors, push buttons, etc.
8. The following locations are reserved for COSA infrastructure, and no network nodes or related equipment shall be installed therein, unless otherwise authorized by the director or designee:
A. any location not on a vertical support pole (i.e., steel mast arm mounted over the roadway, span wire cable between poles, down guy cable systems, etc.)
B. within ten (10) ft. from the base of the pole (any type of traffic signal pole)
C. within three (3) ft. below the mast arm on the pole
D. within five (5) ft. above the mast arm on the pole
E. within five (5) ft. from the top of the pole
9. When approved pursuant to applicable procedures and reviews, including load analysis, extensions may be mounted to poles to permit installation of a network node or related equipment.
10. Applicants shall be responsible for ensuring that installation of equipment and approved extensions shall not encroach into areas restricted by CPS surrounding primary, secondary, and neutral wires.
11. All pole excavations, construction activities, and aerial installations on poles in the ROW shall be carried on as to minimize interference with the use of city's public ROWs and with the use of private property, in accordance with all regulations of the City necessary to provide for public health, safety and convenience.
12. Network providers shall not install overhead lines connecting to a network node collocated on a service pole or a node support pole, unless approved by the director for temporary maintenance or repair not to exceed ten (10) days. All lines, including power and transport facilities, connecting to a pole mounted network node, shall be placed in duct or conduit that is buried below ground, provided that a network node attached to a utility pole, a municipally owned utility pole, or a pole not subject to Chapter 284 requirements may connect to aerial transport facilities for which an attachment right has been granted by the utility pole owner.
13. All construction in the ROW shall conform to the latest version of the "City of San Antonio Standard Specifications for Construction" document and associated special provisions, available at on the City of San Antonio's website at http://www.sanantonio.gov/TCI/Current-Vendor-Resources/Standard-Specifications-and-Details, as well as the UECM.
14. Installations with no equipment located on the ground are strongly encouraged. Where ground-mounted equipment is approved as part of a permitted installation, it shall comply with the requirements of this manual.
c. Electrical power charge associated with network nodes installed on certain city infrastructure.
1. The city may allow network providers that locate network node equipment on any traffic signal pole to utilize the city's meter and/or electric service account associated with the host traffic signal pole. Network providers shall pay to the city an annual power fee designed to recover the cost of the additional electric energy used by the network node equipment and related infrastructure installed by the provider on any city traffic signal pole. The initial annual power fee shall be paid on the date a network node application is approved by the city and invoiced annually, on October 1 of each year thereafter. The annual power fee shall be adjusted as necessary to ensure the city receives full cost recovery for network node installations on city traffic signal poles. Similarly, the annual power fee may be adjusted prospectively as necessary to reflect any increase in CPS energy rates. The annual power fee shall be based on the projected kilo-watt-hour consumption, as determined by the maximum wattage/amperage capacity of the installed network node equipment as stated on the right-of-way network node permit application, which is subject to verification by CPS energy.
2. Via the annual power fee specified in subsection c.1., above, a network provider shall reimburse the city for its proportionate share of cost for electricity use, based on wattage/amperage tiers as illustrated in section c.3. below. The city retains the right, at any time, to amend the wattage/amperage range for any tier and related annual power fee, including the creation of additional tiers. For any network node location, if the city determines that the network node equipment is using more kilo-watt-hours than the initial tier designation, the city shall designate an alternative tier to the network node as appropriate. The city retains the right to disconnect power to any network node if the annual power fee is not paid. The city retains the right to require a dedicated meter, at the network provider's expense, for any network node installation at any time if the provider fails to timely pay or repeatedly and significantly underestimates usage.
3. The annual power fee applicable to network node equipment installed on any city traffic signal pole is set out in section 37-22 of the city's municipal Code.
DIVISION IV. GENERAL AESTHETIC REQUIREMENTS
a. Height limits.
1. Maximum pole height.
In accordance with Texas Local Government Code Section 284.103, no new, modified, or replacement utility pole or node support pole installed in a public right-of-way shall exceed the lesser of:
A. Ten (10) feet in height above the tallest existing utility pole located within 500 linear feet of the new pole in the same public right-of-way; or
B. Fifty-five (55) feet above ground level.
2. Supplemental height regulations.
Notwithstanding the height limits in subsection (a), above, all poles and associated equipment shall comply with the height restrictions of the Airport Hazard Overlay District, as found in Section 35-331, Military Airport Overlay Zones, as found in Section 35-344, and Viewshed Protection and Mission Protection Overlay Districts, as found in Sections 35-337 and 35-339.06, of the City Code.
3. Other height regulations.
Network providers shall be responsible for complying with all applicable federal regulations, including applicable Federal Aviation Regulations (FAR) such as those codified at 14 CFR, part 77.
b. Other dimensional limits.
1. Per Texas Local Government Code Section 284.003, except as provided by Section 284.109 of that Code, a network node to which this chapter applies must conform to the following conditions:
A. each antenna that does not have exposed elements and is attached to an existing structure or pole:
i. must be located inside an enclosure of not more than six cubic feet in volume;
ii. may not exceed a height of three feet above the existing structure or pole; and
iii. may not protrude from the outer circumference of the existing structure or pole by more than two feet;
B. if an antenna has exposed elements and is attached to an existing structure or pole, the antenna and all of the antenna 's exposed elements:
i. must fit within an imaginary enclosure of not more than six cubic feet;
ii. may not exceed a height of three feet above the existing structure or pole; and
iii. may not protrude from the outer circumference of the existing structure or pole by more than two feet;
C. the cumulative size of other wireless equipment associated with the network node attached to an existing structure or pole may not:
i. be more than 28 cubic feet in volume; or
ii. protrude from the outer circumference of the existing structure or pole by more than two feet;
D. ground-based enclosures, separate from the pole, may not be higher than three feet six inches from grade, wider than three feet six inches, or deeper than three feet six inches; and
E. pole-mounted enclosures may not be taller than five feet.
2. The following types of associated ancillary equipment are not included in the calculation of equipment volume under Subsection (A):
A. electric meters;
B. concealment elements;
C. telecommunications demarcation boxes;
D. grounding equipment;
E. power transfer switches;
F. cut-off switches; and
G. vertical cable runs for the connection of power and other services.
3. Equipment attached to node support poles may not protrude from the outer edge of the node support pole by more than two feet.
4. All network node equipment placed on new and existing poles shall be located not less than eight feet above ground level.
5. Equipment attached to a utility pole must be installed in accordance with the National Electric Safety Code and the utility pole owner's construction standards, subject to all other applicable codes, regulations, or laws.
c. Lighting.
Network nodes and node support poles shall not be artificially lighted unless required by the FAA, FCC, or other applicable regulatory authority. If required, lighting shall be designed to cause the least disturbance feasible to the surrounding property owners.
d. Advertising.
No sign of any type shall be allowed on a network node, node support pole, or any other component of a wireless antenna installation, transport facility, or any associated equipment, other than notices required by law.
e. Prohibited power sources.
Solar panels and generators are prohibited as part of any network node, node support pole, or any other component of a network node installation, transport facility, or any associated equipment, in the ROW.
f. Visual appearance of equipment.
The installation of all network nodes, node support poles, or other components of a wireless antenna installation, transport facility, or any associated equipment, whether pole-mounted or ground-mounted, shall be of the least visually intrusive type feasible to meet the design performance goals. This shall be achieved by utilization of the dimensionally smallest equipment and equipment enclosures meeting the design specifications for the particular location and function. Additionally, all equipment, conduit, attachment hardware, and other elements installed or modified by a network provider shall be the same color as the pole to which they are attached, or the background against which they are viewed from the ground. Network providers shall minimize the visual obtrusiveness of installations to the greatest extent possible using methods including, but not limited to, integrating the installation with the existing infrastructure components to which they are attached, or utilization of coverings or concealment devices of similar material, color and texture—or the appearance thereof—as the surface against which the installation will be seen or on which it will be installed. Placing conduit and associated wiring inside new network node steel support poles, or of similar material and design support poles, are encouraged and preferred.
g. New or replacement pole aesthetic requirements.
1. Unless noted otherwise, all poles shall be of a size, type, and finish per TCI and subject to section 29-139 of the city Code and applicable federal or state standards.
2. In no event shall new node support poles be placed in front of the front façade of primary structures on any single-family residential lot.
3. For purposes of this manual, structures fronting more than one street shall be considered to have a front façade fronting on each such street.
DIVISION V. ADDITIONAL AESTHETIC REQUIREMENTS IN DESIGN DISTRICTS
a. Applicability.
1. The requirements of Division IV of this Manual shall apply to network node installations in the ROW within all city parks, as well as in the ROW within, or directly abutting property within, Design Districts as defined herein.
2. For purposes of Texas Local Government Code Chapter 284 and this manual, the following types of districts shall be considered Design Districts with Decorative Poles:
A. Downtown 'D'
B. Historic 'H', 'HS', 'HE' or 'HL', including properties within historic districts and individual properties designated as Historic Landmarks
C. River Improvement Overlay 'RIO'
D. Neighborhood Conservation 'NCD'
E. Corridor Improvement Overlay
F. Viewshed Protection 'VP' and Mission Protection 'MPOD'
G. Airport/Military Airport Overlay 'AHOD/MAHOD'
H. Form-Based Zoning District 'FBZD'
The above list is intended for information purposes only, is not intended to be exhaustive, and is subject to amendment.
3. The Design Districts listed above may be further subdivided by neighborhood, area, or other division. Where specific requirements apply within sub-districts, such requirements may be elaborated in this Manual.
4. Where conflicts exist between this Manual and other district-specific or sub-district-specific Design Manuals, the more stringent requirements shall control.
b. Design district aesthetic requirements.
In addition to the design requirements in Division III of this Manual, the following aesthetic requirements shall apply in Design Districts:
1. The installation of new poles is discouraged in Historic Districts, Downtown "D," River Improvement Overlay Districts, Viewshed Protection and Mission Protection Overlay Districts. No new poles are to be reviewed or approved prior to the submission of a documented effort to install network node equipment onto existing poles within the immediate block or a two hundred fifty-foot radius. If installation is found to be infeasible or unproductive to the area's telecommunication network needs, only then may a new pole installation be considered. The historic preservation officer determines if the network provider has shown good cause for granting an exception to the distance requirement. Good cause is determined in the historic preservation officer's sole discretion and, in any event must be based on the unavailability or unsuitability of all other feasible locations.
2. New pole locations should follow the placement pattern of existing pole structures of the immediate block or within a two hundred fifty-foot radius, regarding both the distance between existing poles and the relationship between poles and abutting structures. Typically, appropriate new pole locations include commercial corners or intersections and the corners between properties.
A. New poles in districts designated as design districts in this manual shall be placed within ten (10) feet of interior lot lines.
B. In no event shall new node support poles be placed in front of the front façade of primary structures on any property designated as historic or within one thousand five hundred (1,500) feet of the brass monument viewshed marker in front of a structure designated by the United Nations as a UNESCO World Heritage site.
3. Network nodes, node support poles, and related equipment shall require camouflage or concealment measures to mitigate the impact or improve the aesthetics of the installation, as determined by the historic preservation officer based on the unique circumstances of the design district or impacted property.
A. New network node poles should match the material, color, and general form of existing poles within the immediate block or two hundred fifty-foot radius. Typically appropriate poles to mimic include wood utility poles, metal streetlight poles, and metal traffic poles. The historic preservation officer maintains the discretion to stipulate a higher quality and more appropriate pole material and design when matching the existing poles is counterproductive to the design district. Public art poles or specially designed poles may also be considered in unique circumstances such as an arts and culture district or corridor.
B. New node support poles should blend into the streetscape by using existing familiar forms and functions, rather than calling attention with a new distinct design exclusive to network nodes. For instance, a new node support pole may require the installation of a light arm to prevent the installation of a single-use pole, used solely for mounting network node equipment.
C. Each new, modified, or replacement utility pole or node support pole shall not exceed the lesser of: a) ten (10) feet in height above the tallest existing utility pole located within five hundred (500) linear feet of the new pole in the same public right-of-way; or b) fifty-five (55) feet above ground level. The dimensions of a new pole should be minimized to the greatest extent feasible, while meeting the minimal requirements for concealing equipment inside the pole or withstanding wind or other structural loads by Code.
4. Pole-mounted network node equipment (including, but not limited to, radios, antennas, meters, shrouds, cabinets, and conduit) shall require camouflage or concealment measures, feature a low profile, and be flush mounted to the greatest extent feasible to mitigate the impact or improve the aesthetics of the installation. Typically, appropriate equipment feature simple geometries and concealed conduit, manufactured or painted to match the pole color, and will not feature any branding, messaging, or outstanding utilitarian details.
5. Ground-based enclosures adjacent to a pole, often used for housing meter and disconnect equipment, are strongly discouraged. When concealing within the base of a pole or underground is infeasible, ground-mounted equipment must be integrated into the overall design of an installation, camouflaged or concealed based on site specific conditions, and positioned to mitigate visual or physical obstructions to nearby historic and design features as recommended by the historic preservation officer. In some site specific conditions, ground equipment may be concealed by the use of existing or new streetscape elements, such as recycling bins, park and bus stop benches, bike racks, or planters.
c. Decorative poles.
In accordance with Chapter 284, installation or attachment of wireless communications equipment, including antennas, network nodes, transport facilities, and related equipment is prohibited on all decorative streetlight poles in Design Districts.
(Ord. No. 2017-08-31-0609, § 1, 8-31-17; Ord. No. 2020-04-02-0225, § 1, 4-2-20)