Sec. 19-43. - Floodways.
(a) Except as may be otherwise provided in this chapter, no floodplain development permit shall be issued for a development to be located in any floodway, or any special flood hazard area for which a floodway has not been designated, if that development provides for:
(1) Encroachment by the deposition of fill, or other similar construction, within the floodway, or the special flood hazard area if no floodway has been designated; or
(2) New construction, any addition to an existing structure, or substantial improvement of any structure within the floodway, or the special flood hazard area if no floodway has been designated.
The general restriction does not apply to a repair or renovation that is not a substantial improvement.
(b) For those facilities necessary to protect the health, safety and welfare of the general public, the city engineer may issue a floodplain development permit for development of a site or the new construction, addition to an existing structure, or substantial improvement of a structure within the floodway, or any special flood hazard area for which a floodway has not been designated, if a professional engineer licensed in the State of Texas submits supporting documentation or an engineering analysis acceptable to the city engineer and written certification to the effect that:
(1) The cumulative effect of the proposed development when combined with all other existing development, and if a floodway has not been designated, all anticipated development, will not have an adverse effect on flood levels at any point within the city during occurrence of the base flood;
(2) The development will not impede the flow of floodwaters; and
(3) The development will not result in an adverse effect on the conveyance capacity during the occurrence of the base flood.
(c) The city engineer shall issue a floodplain development permit for development for an addition to, or for the replacement or substantial improvement of, a structure in a floodway, or any special flood hazard area for which a floodway has not been designated, if the city engineer determines that:
(1) The bottom of its lowest horizontal structural member will be elevated at least three feet above the 0.2 percent chance flood level;
(2) The foundation system for the structure will be elevated floor construction; and
(3) The applicant has paid all fees required by section 19-17(e) of this Code.
If the city engineer cannot so determine, then the city engineer shall deny the floodplain development permit.
(d) While the community acknowledges the increased risks associated with development on vacant land in the floodway, the city engineer shall issue a floodplain development permit for a development in a floodway, or any special flood hazard area for which a floodway has not been designated, if the city engineer determines that:
(1) The bottom of the lowest horizontal structural member of the structure will be elevated at least two feet above the 0.2 percent chance flood level;
(2) The foundation system for the structure will be elevated floor construction;
(3) The applicant has submitted an engineering analysis acceptable to the city engineer, certified by a professional engineer licensed in the State of Texas, that demonstrates that the applicant will provide floodway conveyance offset volume at a rate defined by the city engineer. The floodway conveyance offset volume may be provided on applicant's site or at an off-site mitigation facility located within one-quarter mile upstream and in the same watershed as the site. If the applicant chooses to provide off-site mitigation, the applicant shall also comply with the requirements of section 19-17(c); and
(4) The applicant has paid all fees required by section 19-17(e) of this Code.
(e) The city engineer shall issue a floodplain development permit for development for the construction of a bridge, or the repair or replacement of an existing bridge in a floodway, or any special flood hazard area for which a floodway has not been designated, if the city engineer determines that:
(1) The cumulative effect of the proposed construction when combined with all existing development, and if a floodway has not been designated, all anticipated development, will result in a zero increase in flood levels at any point within the city during occurrence of the base flood; and
(2) The bottom of the lowest horizontal structural member of the bridge, excluding the pilings or columns, will be elevated at least 18 inches above the base flood level, or at least the 0.2 percent chance flood level, whichever is higher. If the city engineer determines that construction to this elevation is not practical based upon the application of sound engineering principles to the proposed construction, the elevation geometry, the attendant roadway geometry, and the necessity for the bridge to be built or reconstructed in the proposed location, the city engineer may approve a deviation from this standard.
If the city engineer cannot so determine, then the city engineer shall deny the floodplain development permit.
(f) If the city engineer denies a floodplain development permit pursuant to section 19-43(a), (b), (c) or (e) of this Code, and the general appeals board finds and determines in writing that:
(1) The improvement is insubstantial;
(2) The insubstantial construction will not increase flood levels during occurrence of the 0.2 percent chance flood; and
(3) The insubstantial improvement will not impede the flow of floodwaters;
then the city engineer shall issue a floodplain development permit only if the other applicable provisions of this chapter have been met by the applicant for the floodplain development permit.
(Ord. No. 2018-258, § 2(Exh. A), 4-4-2018)