Coordination.
23 C.F.R. § 635.307
in effectEffective (a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.
(b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:
(1) 23 CFR part 140, subpart I;
(2) 23 CFR part 646, subpart B;
(3) 23 CFR 710.403; and
(4) 23 CFR part 645, subpart A.
Source: eCFRURL: https://www.ecfr.gov/api/versioner/v1/full/2024-07-01/title-23.xmlFetched: 7/26/2026