33.475.210 River Setback

A. Purpose. The purpose of the river setback is to keep structures separated from the river in areas where the land is not being reserved for river-dependent and river-related uses. Separating structures from the river facilitates protection, maintenance, restoration, preservation and enhancement of the natural, scenic, historic and recreational qualities of the Willamette River by reserving space for the conservation and enhancement of natural vegetation and the opportunity for public access. In addition, OAR 660-015-0005 requires the establishment of a setback line. B. General. The requirements of this section focus on whether the development is river- dependent or river-related. The focus is not on the primary use of the land. For example, in the River General overlay zone, a marine transportation terminal is a river-dependent primary use, but not all development associated with the terminal is river-dependent. The dock is river-dependent, but the parking lot and offices are not. C. The river setback. The river setback extends from the top of the bank to a point 50 feet landward of the top of bank. See Figure 475-1. Top of bank is shown on Map 475-2. Where top of bank is not shown on Map 475-2, top of bank is determined as described in 33.910.030, Definitions, and 33.930.150, Measuring Top of Bank. Where top of bank is shown on Map 475-2, applicants may choose to determine top of bank as described in 33.910.030, Definitions, and 33.930.150, Measuring Top of Bank. Where alteration to the river bank carried out to meet 33.475.440.H results in the top of bank shifting landward, the applicant may choose to measure the setback from the original top of bank. When this occurs, a survey of the original top of bank line and new top of bank line must be submitted for verification that the top of bank has been measured according to the standard in 33.930.150, Measuring Top of Bank, and then recorded with the County recorder. In all cases the river setback line must be at least 5 feet landward of the new top of bank line. Figure 475-1 River Setback

![](https://figures.74-208-44-221.nip.io/portland/20261114/1781fef4abdcb4a59da4bdd50a1a637d1f963fa996205455251b3d41f1e50e7b.png)

![Figure 475-1 River Setback](https://figures.74-208-44-221.nip.io/portland/20261114/4c607713da56c342cfe33a344fcdf23caca3422f7972b2fa6bc2e642b0e9dd58.png)

D. River setback standards. 1. Development landward of the river setback. Development, exterior alterations, excavations, and fills landward of the river setback are not required to be river- dependent or river-related. 2. Development within or riverward of the river setback. Except as follows, development, exterior alterations, excavations, and fills within or riverward of the river setback must be river-dependent or river-related: a. Development, exterior alterations, excavations, and fills that are not river- dependent or river-related are allowed to encroach into the river setback as described in Subsection E. Development, exterior alterations, excavations, and fills located riverward of the setback must be river-dependent or river-related, except as allowed by 33.475.250.D; b. Development within a Historic or Conservation landmark located within or riverward of the river setback is not required to be river-dependent or river- related, and the floor area of the landmark and the exterior improvement area associated with the landmark can be increased up to a total of 10 percent within the river setback when the alteration does not bring the building or exterior improvement area closer to the river. c. All other development, exterior alterations, excavations, and fills that are not river-dependent or river-related are allowed if approved through a Greenway Goal Exception. E. Encroachment into the setback. Development that is not river-dependent or river-related may encroach up to 5 feet into the river setback provided that the setback is increased by an area equivalent in size to the encroachment area. The area that is increased must be located adjacent to the original setback. See Figure 475-2. Figure 475-2 Encroachment into the River Setback

![](https://figures.74-208-44-221.nip.io/portland/20261114/4a811e4b0fc016cecc41c9b581089bc3240d8c9ebbad8a33f1ed00bb795ef968.png)

![Figure 475-2 Encroachment into the River Setback](https://figures.74-208-44-221.nip.io/portland/20261114/c18ebe86018aa4fc35279f12d328b7fa569e64826a10f5bde10c192b0b88f4c7.png)

Ask a question about Portland law

Corpus searches the Portland sections it holds and shows the ones that match, with their citations. Free, no sign-in.