Sec. 59.604. - Capacity Reservation Fees for Capacity Reservation Certificates.
A capacity reservation fee shall be required for all capacity reservation certificates. A reservation fee equivalent to 33% of estimated sewer impact fees shall be paid in order to reserve capacity for up to one year. A reservation fee equivalent to 67% of estimated sewer impact fees shall be paid in order to reserve capacity up to two years and a reservation fee equivalent to 100% of estimated sewer impact fees shall be paid in order to reserve capacity up to three years. At the time of application for a Capacity Reservation Certificate, the applicant shall be required to pay the reservation fee and a separate Reservation Administration Fee as a condition of capacity reservation. If the applicant is not reserving capacity for the entire project the fees shall only be for the actual capacity being reserved and not for the entire project. The applicant shall have 90 calendar days from issuance of a Concurrency Encumbrance Letter to remit all fees. Failure to make payment within this time frame shall be deemed to be a withdrawal of the application for CRC and the CMO shall remove the encumbered capacity.
The applicant shall be required to pay all sewer impact fees due at the time of, and as a condition of, receiving a building permit, pursuant to the impact fee rate schedule in effect at the time a building permit is issued. However, the reservation fee shall be credited toward sewer impact fees applicable at time of building permit on a dollar-for-dollar basis. No credit is allowed for the Reservation Administration Fee.
Reservation Fees
Up to 1 Year | Up to 2 Years | Up to 3 Years
Reservation Fee equal to | 33% of sewer impact fees | 67% of sewer impact fees | 100% of sewer impact fees
Administration Fee | 2% of reservation fee or $2,000, whichever is less | 2% of reservation fee or $2,000, whichever is less | 2% of reservation fee or $2,000, whichever is less
Possible refund | 90% refund of reservation fee | 80% refund of reservation fee | 70% refund of reservation fee
(Ord. of 9-16-1991, Doc. #25096; Ord. of 11-16-1992, Doc. #26149; Ord. No. 2017-4, § 1(Exh. A), 2-27-2017, Doc. #1702271206; Ord. No. 2024-39, § 3, 9-23-2024, Doc. #2409231305)