Additional construction defects
HRS §672E-9
in effect672E-9. Additional construction defects
A construction defect discovered after the notice of claim is served may not be alleged in an action until the claimant has given the contractor:
(1) A written notice of claim regarding the alleged
defect under section 672E-3; and
(2) An opportunity to repair the construction defect
or reject the notice of claim under section 672E-4.
[L 2004, c 119, pt of §2]
Source: Hawaii State Legislature (capitol.hawaii.gov), via Internet Archive capturesURL: http://www.capitol.hawaii.gov/hrscurrent/Vol13_Ch0601-0676/HRS0672E/HRS_0672E-0009.htmFetched: 11/10/2026