Sec. 19-348. - Administrative enforcement.
(a) Stop work orders. A stop work order shall be in writing, state the work to be stopped, state the reasons therefore, and state the conditions under which the work may be resumed. A stop work order may be issued for:
(1) Working in the right-of-way without a valid and unexpired utility right-of-way master permit or unrevoked and unexpired franchise issued by the city as required by section 19-336;
(2) Use of a contractor that has not been registered with the city other than in an emergency;
(3) Violation of subsection 19-338(c);
(4) Violation of subsection 19-340(c);
(5) Failure to comply with subsection 19-338(b) within a reasonable period of time after notification of such non-compliance;
(6) Failure to comply with subsection 19-340(b) within a reasonable period of time after notification of such non-compliance;
(7) Violation of subsection 19-341(b);
(8) Violation of subsection 19-341(c).
(b) Permit denials. The city may refuse to issue utility work permits required by this article to a utility that does not possess a valid and unexpired utility right-of-way master permit or unrevoked and unexpired franchise as required by section 19-336 or to a utility that is in violation of the terms and conditions of a utility right-of-way master permit or franchise.
The city may refuse to issue utility work permits required by this article to a utility that has not paid civil penalties within 45 days after the date the penalties were assessed if the company has not appealed the assessment, or within 45 days of a final decision on appeal.
The city may refuse to issue utility work permits required by this article to a utility that has not paid costs assessed pursuant to subsection (c) within 45 days of the assessment.
(c) Cost of remediation. In the event that a utility fails to properly repair and restore the right-of-way as required by this article, the city may provide of the repair and restoration and charge the cost to the utility.
(Ord. No. 3730, § 1, 10-22-2007)