Evaluation process.
Biloxi Code of Ordinances § 5-17-9
in effectSec. 5-17-9. - Evaluation process.
(a) The evaluation process for determining the need for in-building amplification is conducted in a minimum of two phases: pre-construction and acceptance/implementation.
(b) Pre-construction phase.
(1) Before the construction of the new building, basic information can be gathered to begin the process of determining the need, type and actual implementation of augmentation to the radio system. In most cases, the following information must be known to properly design and cost estimate an in-building radio system.
a. New building information:
1. Type/size of building—Single story, multi-level, square footage, number of stories.
2. Orientation of building—Above/below ground, line of sight.
3. Construction of the outer and inner walls—Plaster, drywall, brick, sheet metal.
4. Proposed equipment locations—Equipment rooms, cableways, conduits.
5. Building location—Longitude and latitude coordinates.
6. Local building code requirements and special requirements.
7. Building blueprints and drawings.
(2) Existing system information—To be supplied by Harrison County Emergency Communications Commission.
a. Public safety radio network site location nearest to construction locations.
b. Donor channel frequency—Specific digital channel to enhance radio coverage.
c. Grade of service required to meet coverage requirements.
d. Type of subscriber unit.
e. Number of channels and their frequencies.
f. Signal strength of donor site at the building locations.
With the information above, the following steps can establish the potential need for a building amplifier.
(3) Needs determination—Signal strength measurements.
a. At the planned construction site, measure (or have measured) the signal strength of the donor control channel.
b. If the signal strength of the donor is -95 dBm or less on the outside of the building, the probability of additional in-building coverage is high.
c. If the signal strength of the donor is greater than -95 dBm, determine the expected signal strength of the donor by subtracting the sum of the interior losses due to walls, doors, and windows from the ambient signal outside the building. (See Table 1)
d. If a signal strength of -95 dBm or greater is calculated at the inner most point of the building, an in-building system may not be required.
e. If a signal strength is calculated at -95 dBm or less, an in-building system is warranted.
f. To determine signal strengths for specific areas and evaluate the impact of the proposed building on existing structures, consult the latest Harrison County Emergency Communications District RF Survey Report.
g. If determined that an in-building amplification system is required for either the proposed site or existing structures impacted by the proposed construction, provide placeholder in budget for cost of communication system based on results of the above.
(Ord. No. 2026, § 2, 3-7-06; Ord. No. 2352, § 2, 2-20-18)
Source: City of Biloxi, Mississippi, Code of Ordinances and Land Development Ordinance (Municode Library, library.municode.com)URL: https://library.municode.com/ms/biloxi/codes/code_of_ordinances?nodeId=COOR_CH5BU_ARTXVIIEMRASYCO_S5-17-9EVPRFetched: 11/1/2026