§ 211 — Wastewater facilities impact fee required as a condition precedent to the development of certain property; procedures, rights and obligations related thereto
Land Development Code, City of Coral Springs, Florida (Supp. No. 76, Update 2: codified through Ordinance No. 2025-119, enacted December 3, 2025) · Coral Springs Land Development Code § 211
Corpus is an independent public-information project, not the official City of Coral Springs website. Stable reference: corpuslaw.us/code/f74402f7-bb69-4185-93e1-be39a031950b
Sec. 211. - Wastewater facilities impact fee required as a condition precedent to the development of certain property; procedures, rights and obligations related thereto.
(a) Intent. The WWFIF shall be a fee which shall be determined at site plan approval, and is payable prior to the issuance of a building permit by the city. The WFIF is based upon the water facility demand attributable to the new connections and the cost of providing the wastewater facilities needed to serve new connections. (b) Definitions. As used in this section, the following words and terms shall have the following meaning: (1) Applicant means the property owner, or duly designated agent of the property owner, of land on which a building permit is requested and a WWFIF is due pursuant to this section. (2) Encumbered means a contract has been let for construction of the designated improvement. (3) Impact fee means a monetary exaction imposed on a pro rata basis in accordance with the demand for off-site wastewater facilities created by the development. (c) Designation of wastewater service area. The wastewater service area is the area as designated as Map 1, Page 7a-1A, Sanitary Sewer, Solid Waste, Drainage, Potable Water and Natural Groundwater Aquifer Recharge Elements, City of Coral Springs Comprehensive Plan, as may be amended from time to time. The official map shall be maintained in the office of the city clerk. (d) Imposition of wastewater facilities impact fee. (1) No building permit shall be issued by city unless the applicant has paid the applicable WWFIF impact fees pursuant to this section. Any building permit issued by the city, without payment by the applicant of the applicable impact fee pursuant to this section, shall be void ab initio. (2) The issuance of a building permit shall comply with all applicable land development regulations and city ordinances, as may be amended. (e) Exemptions. (1) The WWFIF shall not be applicable to building permits otherwise necessary for public schools pursuant to F.S. Ch. 1013. (f) Calculation of impact fee. The city shall calculate the impact fee as follows: (1) For residential developments, multiply the number of dwelling units by the applicable impact fee adopted pursuant to resolution by the city commission. (2) For nonresidential developments, an impact fee shall be charged per meter and by meter size at a rate adopted pursuant to resolution by the city commission. (g) Administration of impact fees. (1) Calculation of impact fees. Impact fees calculated and imposed pursuant to this section shall be collected by the city prior to issuing a building permit. (2) Transfer of funds to finance department. WWFIFs shall be placed in the wastewater facilities improvement trust fund account which shall be established pursuant to this section. (3) Wastewater facilities improvement trust fund. a. The city's finance department shall establish a wastewater facilities improvement trust fund, in an interest-bearing account, for deposit of all WWFIF collected. b. Interest earned on the account shall be considered funds of the wastewater facilities improvement trust fund and shall be used solely for the purposes specified. c. The city's finance department shall maintain and keep financial records for the trust fund account, showing the source and disbursement of all revenues. d. Trust fund account(s) shall be accounted for by the name of the property owner and/or the name of the development. (4) Use of funds collected. a. The impact fees assessed and collected pursuant to this section shall be used exclusively for the purpose of undertaking wastewater facilities projects or for financing directly, or as a pledge against bonds, revenue certificates and other obligations of indebtedness, to finance the project costs of wastewater facilities projects as approved by the city in the five-year capital improvement program, including the cost of upgrading or improving existing wastewater facilities in order to meet the need for new wastewater capacity generated by new development, and consistent with the comprehensive plan. All WWFIF funds shall be used for wastewater facilities projects within the city's wastewater service area and/or pursuant to the large user agreement with the county. b. WWFIFs collected pursuant to this section shall not be used to pay any of the following expenses: 1. Operation, maintenance or repairs of existing wastewater facilities. c. Funds withdrawn from the trust fund account must be used solely in accordance with the provisions of this section. The disbursal of such funds shall be in accordance with the five-year capital improvement program of the city and the large user agreement with the county. The disbursal of such funds for a water facilities project not presently in accord with the applicable capital improvement element of the city's comprehensive plan, or the five-year capital improvement program of the city, may occur if the commission adopts findings of fact, supported by competent evidence and data, concerning: 1. The need for the wastewater facilities project, in whole or in part, due to demand and attributable to new connections; and 2. The consistency of the wastewater facilities improvements (projects) with the city's comprehensive plan and specific elements thereof; and 3. The consistency of the wastewater facilities improvements with the purpose and intent of this section; and 4. The history of the wastewater facilities improvements, including, but not limited to, whether the need for the wastewater facilities improvements had been identified in prior capital improvement elements of the city's comprehensive plan, and the five-year capital improvement program. (h) Refunds; standards and procedures under certain circumstances. (1) In the event an applicant has paid an impact fee into the city's wastewater facilities trust fund as payment pursuant to the WWFIF, and the density or intensity of development is less than the assumptions used for calculation of said fees, or in the event an applicant has paid an impact fee pursuant to the WWFIF and said fee is not encumbered within five (5) years, then the applicant shall be entitled to a pro rata refund of fee unless the city makes a finding that: a. Identifies the specific wastewater facilities projects listed in the first two (2) years of the current capital improvements plan for which the WWFIF will be expended, and the year in which the wastewater facilities project will be constructed; and b. Demonstrates that a "rational nexus" exists between the impact fee and the wastewater facilities projects needed to serve the applicable use. (2) The applicant must petition the city for the refund within one (1) year following the five-year period, or extension thereof, granted pursuant to subsection (h)(1)a. and b. of this section. The time for filing a refund petition shall run from the date on which the WWFIF was paid. (3) The petition for a refund must be filed with the city manager and contain the following information: a. A notarized sworn statement that the petitioner is the current owner of the property; b. A copy of the dated receipt issued for payment of the impact fee; c. A certified copy of the latest recorded deed for the property; and d. A copy of the most recent ad valorem tax bill for the property. (4) No later than thirty (30) calendar days from the date of receipt of the petition for refund, the city manager shall present the petition to the city commission at a scheduled public meeting. If the city commission determines that the petition meets all the requirements for a refund, the city shall issue the refund within thirty (30) calendar days of approval by the city commission. Any interest that may have been earned on such amounts shall not be refundable. (5) Refunds requested pursuant to the cancellation or abandonment of a building permit must be submitted within six (6) months of the date of cancellation or abandonment of the building permit. Refund requests under this subsection are not required to submit petitions pursuant to subsection (h)(3) of this section of the Land Development Code; however, proof of entitlement to refund must be submitted to the building department. (6) To reimburse the city for the expense of processing the refund request, the city shall charge the petitioner an administrative fee. Said charges shall be approved by the city commission, by resolution, no later than six (6) months after the adoption of this section. (i) Credits. (1) Any applicant subject to the WWFIF shall be eligible for a credit for such contribution against the WWFIF otherwise due upon submitting a petition for credit to the city manager, if the applicant: a. Elects to undertake all or a portion of an off-site wastewater facilities project; b. At the request of the city, constructs on-site wastewater facilities with capacity in excess of that required to serve the development covered by the building permit; or c. Escrows money with the city to pay for the construction or improvements of an off-site wastewater facilities project. d. Has previously paid impact fees, then any previously paid impact fees shall be credited towards the new impact fee. (2) The amount of credit shall be based upon certified cost estimates submitted by the applicant and upon the recommendation of the director of public works and city manager. The amount of credit shall be approved by the city commission, at a public meeting. In no event shall the credit exceed the amount of the otherwise applicable impact fee. (3) Within ten (10) days after receipt of a petition for credit, the city manager shall forward the petition and supporting documentation to the director of public works for review and recommendation. The city manager, together with the director of public works, shall make a recommendation to the city commission. The petition for credit shall be presented to the city commission, at a public meeting, no later than thirty (30) calendar days after receipt of the petition for credit. The city commission shall approve, deny, or approve with conditions, the petition and establish the amount of the credit. (4) If the petition for credit is approved, or approved with conditions, by the city commission, the applicant and the city shall enter into a credit agreement which shall provide for the timing of the action to be taken by the applicant and the obligations and responsibilities of the applicant and city. The obligations and responsibilities of the applicant may include, but are not limited to, the land acquisition and construction standards and requirements to be complied with; the obligations and responsibilities of the city include, but are not limited to, inspection of the project and the amount of the credit. If the credit is less than the impact fee otherwise due, the applicant shall pay the impact fee, less the credit, prior to the issuance of the building permit. a. Property owners may utilize credits granted toward satisfaction of impact fees due for new development on the same site or on another site provided that the city and the property owner enter into an appropriate written agreement encumbering and allocating the amount of credit to the affected development(s), providing for transferability where appropriate and reducing the overall credit available by the amount agreed upon. (5) Any credits granted by the city commission are hereby deemed the property of the applicant responsible for the creditable improvements and may not be assigned to future purchasers in order to satisfy their WWFIF requirements without prior approval of the city commission. (j) Annual review. (1) Prior to October 1st of each year, in conjunction with the city budget process, the city manager, with the assistance of the public works department, shall prepare a report to the commission on the subject WWFIF, which report shall incorporate: a. Recommendations on amendments, if appropriate, to this section. b. Proposed changes to the impact fee calculation methodology; c. Proposed changes to the impact fee calculation variables; d. Proposed changes to the impact fee rates or schedules. (2) The city manager, in preparing the annual report, shall obtain and review the following information: a. A statement from the finance department summarizing impact fees collected and disbursed during the preceding year for wastewater facility projects and/or the large user agreement with the county; b. A statement from the director of public works summarizing the city's wastewater facility projects initiated and completed during the preceding year by the city; c. A statement from the building department summarizing the building permits issued, by type, during the preceding year; d. A statement from the public works department that the wastewater facility projects undertaken with impact fee funds are consistent with the adopted capital improvement program and comprehensive plan and/or the large user agreement with the county. (3) Based on the annual reports and such other factors as the city commission deems relevant and appropriate, the city commission may amend this section. (4) Nothing herein precludes the city commission or limits its discretion to amend this section at such other times as may be deemed necessary. (k) Appeals. (1) After determination of the amount of the WWFIF, the amount of the credit or the amount of the refund due, the applicant may appeal such determination to the city commission. The applicant must file a notice of appeal with the city within thirty (30) calendar days following the determination of the amount of the impact fee, the amount of the credit or the amount of the refund due. If the notice of appeal is accompanied by a bond or other sufficient surety as determined by the city commission, in an amount equal to the impact fee and surcharge as calculated herein, the city shall issue a building permit. The filing of an appeal shall stay the issuance of the building permit unless such bond or other surety has been filed. (2) Within ten (10) calendar days after filing, the city clerk shall forward the notice of appeal to the city manager's office for appropriate action. A public hearing shall be held by the city commission no later than thirty (30) calendar days after filing of the notice of appeal. (3) Following a public hearing, and based upon a finding that a specific application of this section is not consistent with the meaning and intent of the city commission in the adoption of the WWFIF, the city commission may grant such relief as it determines is fair and equitable under the existing circumstances. (4) The applicant shall be assessed the cost of the required public hearing. (l) Penalties for failure to remit impact fees or construct improvements. (1) Penalty. Failure to remit impact fees or construct improvements required by this section shall constitute a violation of the Land Development Code and shall be punishable as provided herein. (2) Withholding or revocation of city permits. Failure of any party to comply with the requirements of this section shall constitute grounds for withholding site plan approval, building permits, occupancy permits or any other appropriate approvals necessary to continue development. Such sanctions shall be instituted immediately upon the direction of the city manager and with the ratification of the city commission at its next regular or special meeting. The revocation of existing permits or approvals, however, shall be deemed an extraordinary sanction and shall be approved only after public hearing, with notice to the property owner, an opportunity to be heard by the commission and the right to be represented by counsel at that hearing prior to any final action being taken by the city. (3) Other enforcement. Nothing in this section shall prohibit the city from enforcing this section by other means. (m) Effect of the impact fee on zoning and subdivision regulations. This section shall not affect, in any manner, the permissible use of the property, density of development, design and improvement standards and requirements, or any other aspect of the development of land or provision of public improvements subject to the land development regulations or other regulations of the city and/or county which shall be operative and remain in full force and effect, without limitation, with respect to all such development. (n) Impact fee as additional or supplemental requirement. The payment of impact fees are additional to, and not in substitution of, any other requirements imposed by the city and/or county on the development or the issuance of a building permit. In no event shall a property owner be obligated to pay for off-site wastewater facilities projects, in an amount exceeding the amount calculated pursuant to the WWFIF; provided, however, that a property owner may be required to pay, pursuant to city ordinances, regulations or policies, for other public facilities in addition to the impact fee for wastewater facilities projects as specified herein. Such fee is intended to be consistent with, and further the policies of, the city's comprehensive plan, the Municipal Code, [the Land Development Code,] and other city policies, ordinances and resolutions by which the city seeks to ensure the provision of public facilities concurrent with the impacts of development of land.
(Code 1972, § 5-12.8; Ord. No. 2014-111, § 2, 8-20-14; Ord. No. 2023-101, § 29, 4-19-23)
Ask a question about Coral Springs law
Corpus searches the Coral Springs sections it holds and shows the ones that match, with their citations. Free, no sign-in.