Construction of transmission line not prohibited.
MCL 460.1157
in effect460.1157. Construction of transmission line not prohibited.
Sec. 157.
This part does not prohibit an electric utility, affiliated transmission company, or independent transmission company from constructing a transmission line without obtaining an expedited siting certificate.
2008, Act 295, Imd. Eff. Oct. 6, 2008
[Compiler] Enacting section 1 of Act 295 of 2008 provides: "Enacting section 1. As provided in section 5 of 1846 RS 1, MCL 8.5, this act is severable."