14.15.110 - Electrical service provided.

A. The city provides 60-hertz alternating current, either single or three phase, at available standard voltages. Voltage, frequency and wave form are regulated to conform to the standard practices of the industry. B. Standard voltages: 120/208v | Single Phase | Secondary 120/240v | Single Phase | Secondary 120/208v | Three Phase | Secondary 240/480v | Three Phase | Secondary 120/240v | Three Phase | Secondary 480v | Three Phase | Secondary 277/480v | Three Phase | Secondary 7,200/12,470v | Three Phase | Primary 14,400/24,900v | Three Phase | Primary C. The city shall, unless otherwise provided, construct, operate and maintain the facilities necessary to deliver electrical energy to the point of service connection to the service equipment owned by the customer. Responsibility for the design of the city's lines and other facilities shall rest with the city. D. The city will not construct any service unless the approved service equipment is installed and available for connection. If the city's work crew or city's contractor is required to return to the customer's job site due to a lack of appropriate facilities, the customer will be responsible for all actual charges associated with additional trips.

(Ord. 504, 1982; Ord. 95-06)