§ 14.15.720 — Procedures for responding to inquiries from QFs
City Code of the City of Seward, Alaska (Codified through Ordinance No. 2026-006, enacted July 27, 2026. (Supp. No. 33-1, Update 1)) · Seward City Code § 14.15.720
Corpus is an independent public-information project, not the official City of Seward website. Stable reference: corpuslaw.us/code/b43249d7-93a0-4e73-8a25-51999cf20d6f
14.15.720 - Procedures for responding to inquiries from QFs.
A. Upon receiving a written request by a QF to sell power to the utility, the utility shall provide to the requesting QF a copy of the utility's "standard form contract" for interconnection, power purchases, and power sales with a QF. The standard form contract shall be adopted, and modified from time to time, by council resolution. The standard form contract shall not constitute an offer by the utility to interconnect, purchase power, or sell power. Instead, the standard form contract is intended solely to inform the QF regarding some of the general terms and conditions that would typically apply to such transactions with a QF. The standard form contract shall contain a number terms which will require negotiation between the utility and the QF with respect to the specific circumstances of the QF project being proposed. B. After reviewing the standard form contract, the QF shall notify the utility in writing if it desires to further pursue selling power to the utility. C. If the QF desires to further pursue selling power to the utility, the utility shall notify the QF regarding what information the QF must provide to enable the utility to (1) accurately calculate its avoided cost and (2) determine what contract terms and conditions are appropriate given the specific circumstances of the proposed QF project (facility). D. The information to be provided by the QF under (C) shall be determined by the utility; such information may include, but shall not be limited to, the following: 1. Detailed description of the facility; 2. Detailed explanation demonstrating that the facility qualifies as a "qualifying facility" as that term is defined in 18 C.F.R. Part 292; 3. Precise location of the facility; 4. Nameplate electric generating capacity, net electric energy output, and plant factor of the facility; 5. Minimum and maximum availability of firm capacity and/or energy from the facility during the utility's daily and seasonal peak periods; 6. Projected date on which deliveries of capacity and/or energy would commence; 7. Plans for facility construction; facility financing; and the acquisition of all necessary property rights, permits, authorizations, and fuel contracts; 8. Expected and demonstrated annual and seasonal reliability of the facility; 9. Periods of scheduled maintenance and outages; 10. Plans for dispatchability of the facility; 11. If applicable, plans for acquiring access to adequate firm transmission services and the terms and conditions of such access; and 12. Any other information the utility deems appropriate under (C) of this section. E. In addition to the requirement in (C) of this section, the QF shall advance to the utility a cash deposit in the amount of the utility's estimated total costs of performing computer modelling to calculate the utility's avoided costs associated with the specific characteristics of the facility, plus a contingency margin of ten percent. After all final calculations of the utility's avoided costs are complete, if the actual costs incurred by the utility to perform such modelling are less than the amount advanced by the QF, the utility shall refund the difference to the QF within 30 days. If the actual costs incurred by the utility exceed the amount advanced by the QF, the QF shall pay the utility the difference within 30 days. F. After the QF has satisfied all requirements provided for in (C) through (E), the utility shall initiate the collection and analysis of whatever data are necessary for the utility to fulfill its obligations under FERC's cogeneration and small power production regulations. Within a reasonable period of time after the QF has satisfied all the requirements provided for in (C) through (E), the utility staff shall take one of the following actions: 1. Initiate negotiations with the QF for a contract specifying the charges, rates, terms, and conditions of interconnection, purchases, and sales between the utility and the QF, in compliance with FERC's cogeneration and small power production regulations; or 2. Notify the city council and any affected QF that, due to special circumstances, the utility is not obligated under FERC's cogeneration and small power production regulations to purchase power from the QF, and provide sufficient explanation to the city council in support of its conclusion. G. If the utility staff initiates negotiations with the QF pursuant to (F)(1) and the utility and the QF are able to successfully negotiate a contract for interconnection, purchases, and sales within a reasonable period of time, the utility staff shall file the contract with the city council for its consideration under the procedures prescribed in section 14.15.725. H. If the utility staff and the QF are not able to successfully negotiate such a contract within a reasonable period of time, or if the utility staff notifies the city council that, due to special circumstances, the utility is not obligated under FERC's cogeneration and small power production regulations to purchase power from the QF, the QF may file a written complaint with the manager of the utility for consideration by the city council under the procedures prescribed in section 14.15.730. I. After public notice in the utility's service area, the utility may at any time apply to FERC for a waiver from its obligations under FERC's cogeneration and small power production regulations. In such event, the procedures provided for in this article 7 may be suspended pending final disposition of the utility's application, including any administrative or judicial appeals.
(Ord. 2000-14, § 1, 2000)
Ask a question about Seward law
Corpus searches the Seward sections it holds and shows the ones that match, with their citations. Free, no sign-in.