Sec. 18-95. - Certificate of appropriateness void if construction not commenced.
A certificate of appropriateness shall become void unless construction is commenced within six (6) months of date of issuance. Certificates of appropriateness shall be issued for a period of eighteen (18) months and are renewable.
(Ord. No. 90-2882A, § 5O, 2-5-90)