§ 14-4 — Change orders

Code of the City of Mobile, Alabama (Supp. No. 67: codified through Ordinance No. 36-017-2026, adopted March 1, 2026) · Mobile City Code § 14-4

Corpus is an independent public-information project, not the official City of Mobile website. Stable reference: corpuslaw.us/code/ceab59c8-b1a2-4730-be3f-2824493881b7

Sec. 14-4. - Change orders.

The mayor is authorized to approve change orders to city construction contracts subject to at least one (1) of the following criteria. All change orders shall be filed in the clerk's office. (1) Minor changes for a total monetary value less than required for competitive bidding under the state competitive bid laws. (2) Changes for matters relatively minor and incidental to the original contract necessitated by unforeseeable circumstances arising during the course of the work. (3) Emergencies arising during the course of the work on the contract. (4) Changes or alternates provided for in the original bidding where there is no difference in price on the change order from the original best bid on the alternate. (5) Changes of relatively minor items not contemplated when the plans and specifications were prepared and the project was bid which are in the public interest and which do not exceed ten (10) percent of the contract price. This shall mean that the total of all change orders on each contract shall not exceed ten (10) percent of the contract price for each project.

(Ord. No. 14-034-2018, § 1, 12-18-18)