Sec. 58-34. - Proof rolling requirements.
Proof rolling of subgrade and base materials shall be performed prior to the placement of curb and gutter, base material and flexible or rigid pavement, as applicable. All tests shall be performed under the direction of the professional engineer responsible for project construction. Said engineer shall notify the office of the city engineer at least 24 hours prior to the proof rolling so that the test may be witnessed, as necessary. Failure of city staff to witness the proof rolling tests in no way relieves contractor or project engineer of their responsibility to comply with these requirements. All proof roll tests will be performed with a rubber-tire tandem-axle dump truck with a minimum gross weight of 45,000 pounds unless otherwise approved in writing by the city engineer. A current weight ticket must be provided at time of the proof roll test to verify loading criteria. Proof rolled material shall show no significant signs of movement during proof rolling.
(Ord. No. 08:006, § 2(9.44.05), 2-19-2008)
Ask a question about Jonesboro law
Corpus searches the Jonesboro sections it holds and shows the ones that match, with their citations. Free, no sign-in.