For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 15.05.020 — Permit expiration

Concord Municipal Code (Current through Ordinance 26-2, passed September 8, 2026) · Concord Municipal Code § 15.05.020

Corpus is an independent public-information project, not the official City of Concord website. Stable reference: corpuslaw.us/code/6fecb1a9-da34-453f-a828-89ff649dfd52

15.05.020 Permit expiration.

Every permit issued by the Building Official under the provisions of this Code shall expire by limitation and become null and void if the work authorized by such permit is not commenced within 12 months from the date such permit is issued, or if the work authorized by such permit is suspended or abandoned for a period of more than 12 months after the work is commenced. Before such work can be recommenced, the permittee must apply for renewal of the permit. Upon approval by the Building Official the permit shall be renewed, and the fee therefor shall be one-half of the inspection fees on the existing permit, provided no changes have been made or will be made in the original plans and specifications for such work; and provided further, that such renewal is applied for within 60 days of permit expiration. For the purposes of this section, the permittee must obtain a passed inspection for work to be considered commenced or active. A permittee holding an unexpired permit may apply for an extension of the time within which the permittee may commence work under that permit when the permittee is unable to commence work within the time required by this section for good and satisfactory reasons. The Building Official may grant one or more extensions of time for action by the permittee for a period not exceeding 12 months per extension upon written request by the permittee showing that circumstances beyond the control of the permittee have prevented action from being taken. Notwithstanding the above provisions, every permit issued by the Building Official under the provisions of this Code shall expire and become null and void if the work authorized by such permit is not completed within three years from the date of issuance of such permit. The Building Official may extend this time on written request by the permittee showing that circumstances beyond the control of the permittee have prevented the completion of the work, and further provided the work has been ongoing and is continuing. The provisions of this paragraph shall apply to permits issued on and after January 1, 2019. (Ord. No. 13-8, § 3; Ord. No. 19-1, § 2 (Exhs. C, D); Ord. No. 19-6, § 2; Ord. No. 20-1, § 2)

Prior legislation: Code 1965 § 9150; Code 2002 § 14-61; Ord. Nos. 99-7, 07-13 and 11-1.

Ask a question about Concord law

Corpus searches the Concord sections it holds and shows the ones that match, with their citations. Free, no sign-in.