§ 15.32.060.5 — Completion time
Municipal Code of the City of El Monte, California (Codified through Ordinance No. 3055, passed June 11, 2025. (Supp. No. 36, Update 1)) · El Monte Municipal Code § 15.32.060.5
Corpus is an independent public-information project, not the official City of El Monte website. Stable reference: corpuslaw.us/code/1f936d77-53b7-42bb-bed2-3edd3d51ca0b
15.32.060.5 - Completion time.
The demolition of any building shall be completed within forty-five (45) days after the issuance of the demolition permit. Demolition shall not be deemed completed until the provision of Sections 15.32.060.3 and 15.32.060.4 of this chapter have been complied with. If before the expiration of the forty-five-day period time a valid building permit has been issued for construction upon the same property, the excavations shall not be required to be filled in unless, in the opinion of the Building Official, a hazardous condition is created by the failure to fill in such excavations.
(Ord. No. 3011, § 3(Exh. A), 6-21-2022)
Ask a question about El Monte law
Corpus searches the El Monte sections it holds and shows the ones that match, with their citations. Free, no sign-in.