§ 33-1317: Expiration and extension of time.
Unless otherwise specified in the action approving a plot plan, said approval shall become automatically null and void unless the project authorized by the plot plan approval has been substantially implemented within 24 months from the approval date. The abandonment or non-use of a plot plan approval for a period of 24 months shall also result in such approval becoming automatically null and void. The director shall have authority to grant extensions to the deadlines in this section. Once any portion of a plot plan is utilized, the other conditions thereof become immediately operative and must be strictly complied with.
( Ord. No. 2017-03R , § 4, 3-22-17 ; Ord. No. 2023-06 , § 3, 3-8-23 )
Ask a question about Escondido law
Corpus searches the Escondido sections it holds and shows the ones that match, with their citations. Free, no sign-in.