§ 11.08.120: Permit Duration.

A. Every permit granted by the City under Sections 11.08.010 through 11.08.040 shall become and be void within 60 days from the date issued. B. The City may extend the time of the permit for a period not to exceed 60 days. C. None of the provisions of this chapter shall apply to work performed under an excavation permit.

( Prior code § 7120.9 ; 2804 § 2, 2011 )