§ 13.44.240 — Feed-in-tariff
Code of Ordinances, City of Glendale, California (Code 2026-05-19) · Glendale Code of Ordinances § 13.44.240
Corpus is an independent public-information project, not the official City of Glendale website. Stable reference: corpuslaw.us/code/2baaf1e6-ecd8-4d7e-8ec2-f9b5500491a9
§ 13.44.240: Feed-in-tariff.
A. Definitions. "Applicant" means an applicant for the FIT Program. "Capacity attributes" means any current or future defined characteristic, tag, credit, or ancillary service attribute, whether general in nature or specific as to the location or any other attribute of the electric generation facility. "Commercial operation" means the period of operation of the electric generation facility once the commercial operation date has occurred. "Commercial operation date" means the date the electric generation facility has successfully completed a test period of 168 hours of continuous operation. During this test, the electric generation facility must meet the following conditions: 1. Comply with all applicable interconnection and system protection requirements; 2. Demonstrate the capability of delivering the contract capacity at the delivery point on a reliable and continuous basis; and 3. Demonstrate that all facility components operate and are available during the 168 hour period. "Contract capacity" means the installed electrical capacity available upon commercial operation of the electric generation facility and specified in the standard form power purchase agreement between the city and the FIT generator. Contract capacity is measured at Glendale Water and Power's power purchase meter at the delivery point, and shall be the electric generation facility's output in kilowatts and any reporting rights associated with such. "Delivery point" means the point of interconnection to Glendale Water and Power's distribution system where the city accepts title to the product from the electric generation facility. "Electric generation facility" means an electric generation facility located within the service territory of, and developed to sell the products to the city and that meets all of the following criteria: 1. Has an effective capacity of not more than 1.4 megawatts (AC), measured at the delivery point. 2. Is interconnected and operates in parallel with the city's electrical transmission and distribution grid. 3. Is strategically located and interconnected to the electrical transmission and distribution grid in a manner that optimizes the deliverability of electricity generated at the facility to load centers. 4. Is certified by the California Energy Commission as an eligible renewable resource as defined by California Public Utilities Code Section 399.12 and California Public Resources Code Section 25471, as either may be amended from time to time. "Energy" means electrical energy delivered to Glendale Water and Power with the voltage and quality required by the city and measured in megawatt-hours ("mWh") or kilowatt-hours ("kWh"). "FIT generator" means a person owning or operating an electric generation facility in the Glendale Water and Power service territory and selling 100% of the products of the electric generation facility to the city pursuant to the FIT program. "FIT program" means the city Feed-in-Tariff Program adopted pursuant to Section 399.32 of the California Public Utilities Code. "FIT program criteria" means the following requirements: 1. Applicant owns or operates an electric generation facility; 2. Applicant provides evidence of site control satisfactory to the city attorney; 3. Applicant submits a complete application with the fees and reservation deposit required in connection therewith (as set forth in the FIT regulations and in such amounts approved from time to time by resolution of council), together with such supporting documents and information as required by the city; 4. Applicant complies with the FIT regulations; 5. If the application is approved, applicant executes and complies with the terms and conditions of the standard form FIT interconnection agreement and the standard form power purchase agreement between the city and FIT generator; and 6. If the application is approved, applicant achieves commercial operation of the electric generation facility within the timelines set forth in the standard form FIT interconnection agreement and the standard form power purchase agreement. "FIT regulations" means the Glendale Water and Power regulations governing the FIT program, adopted and as may be amended from time to time by the council. "Green attributes" means any and all credits, benefits, emissions reductions, environmental air quality credits, offsets and allowances, howsoever entitled, attributable to the generation from the electric generation facility and its displacement of conventional energy generation, whether existing now or arising in the future, including but not limited to renewable energy credits, any avoided emissions of pollutants to the air, soil or water, any avoided emissions of greenhouse gases, and the reporting rights to these avoided emissions. "Greenhouse gas" or "GHG" is a collective term for those gases that reduce the loss of heat from the earth's atmosphere, and thus contribute to global warming and climate change. "Off-peak period" or "off-peak" means all hours other than on-peak period hours including any holidays recognized by the North American Electric Reliability Corporation. "On-peak period" or "on-peak" means the period of time beginning at 6:00 a.m. and ending at 10:00 p.m., Monday through Saturday, excluding any holidays recognized by the North American Electric Reliability Corporation. "Portfolio content category one (PCC1)" means an eligible renewable energy resource interconnected or scheduled into a California balancing authority at the same time of generation pursuant to Sections 399.16(b)(1), 399.16(c)(1) and 399.30(c)(3) of the California Public Utilities Code. "Product" or "products" means energy, contract capacity, capacity attributes, and the green attributes from the electric generation facility and delivered to the city in accordance with the standard form FIT power purchase agreement between the city and the FIT generator. "Renewable energy credit" or "REC" means a certificate of proof that one unit of electricity was generated by an eligible renewable energy resource. RECs are accumulated on a kWh basis and one REC represents the green attributes associated with the generation of one MWh (1,000 kWhs) from the electric generation facility. "Site" means the real property (including all fixtures and appurtenances thereto) and related physical and tangible property generally owned or leased by the applicant where the electric generation facility is located or will be located, and including any easements, rights-of-way or contractual rights held or to be held by applicant for the transmission lines and/or roadways servicing such site or the facility located (or to be located) thereon. "Site control" means that the applicant shall: (1) own the site; or (2) be the lessee of the site under a lease which permits the applicant to perform its obligations under the FIT program. B. Enrollment Process and Eligibility. An owner or operator of an electric generation facility within the service territory of Glendale Water and Power may submit a written application for participation in the FIT program pursuant to the process prescribed in the FIT regulations. Subject to subsection C of this section, the FIT program will be available to applicants meeting the FIT program criteria on a first-come, first-served basis until such time as the city's overall FIT program participation meets the higher of: (1) the maximum FIT program generation capacity required of the city under California Public Utilities Code Section 399.32(2); or such higher amount as may be established by the general manager of Glendale Water and Power. C. Denial of FIT Program Application—Appeal Process. a. The general manager of Glendale Water and Power or designee may deny an application based upon any of the following grounds: i. The electric generation facility does not meet the FIT program criteria or the requirements of this section. ii. The transmission or distribution grid that would serve as the point of interconnection is inadequate. iii. The electric generation facility does not meet all applicable state and local laws and building standards, and utility interconnection requirements. iv. The aggregate of all electric generating facilities on a distribution circuit would adversely impact utility operation and load restoration efforts of the distribution system. b. An applicant that has received a notice of denial from Glendale Water and Power may appeal such denial to the council pursuant to Chapter 2.88 of this code. D. Rates. The energy delivered from the electric generation facility will be measured at the Glendale Water and Power power purchase meter at the delivery point. Payment for the products from the electric generation facility will be made in accordance with the terms of the standard form power purchase agreement between the city and the FIT generator and calculated by Glendale Water and Power on the basis of the following formula rates: On-Peak Period. 1. For energy delivered to Glendale Water and Power during the on-peak period, the avoided on-peak period cost of energy that would otherwise be purchased from the spot or short-term market during the upcoming calendar quarter, using the MEAD_ON forward curve ($/MWH) (as posted by the Intercontinental Exchange [Mead 230 Day Ahead Clearing Price] for on-peak periods); plus 2. The value of portfolio content category one (PCC1) renewable energy credits (RECs) based on recent actual transactions by Glendale Water and Power ($/MWh); plus 3. The avoided greenhouse gas (GHG) compliance costs, which are the product of: (a) the default carbon emissions rate expressed in carbon allowances per megawatt-hour times; (b) the price of carbon allowances from the most recent auction conducted by the California Energy Commission ($/MWH); plus 4. The value of avoided transmission and distribution losses that would occur if energy were purchased on the spot or short-term market and imported into Glendale (8% multiplied by the avoided on-peak cost of energy). Off-Peak Period. 1. | For energy delivered to Glendale to Water and Power during the off-peak period, the avoided off-peak period cost of energy that would otherwise be purchased from the spot or short-term market during the upcoming calendar quarter, using the MEAD_OFF forward curve ($/MWH) (as posted by the Intercontinental Exchange [Mead 230 Day Ahead Clearing Price] for off-peak periods); plus 2. | The value of portfolio content category one (PCC1) renewable energy credits (RECs) based on recent actual transactions by Glendale Water and Power ($/MWh); plus 3. | The avoided greenhouse gas (GHG) compliance costs, which are the product of: (a) the default carbon emissions rate expressed in carbon allowances per megawatt-hour times; (b) the price of carbon allowances from the most recent auction conducted by the California Energy Commission ($/MWH); plus 4. | The value of avoided transmission and distribution losses that would occur if energy were purchased on the spot or short-term market and imported into the city (8% multiplied by the avoided off-peak cost of energy). On a quarterly basis, Glendale Water and Power shall calculate and publish on the Glendale Water and Power website the FIT rates for the on-peak period and the off-peak period, respectively, using the above formula rates. The FIT rates for each calendar year quarter will be effective on the following dates: Quarter | Effective Date 1 | January 1 2 | April 1 3 | July 1 4 | September 1 E. Standard Form Agreements; Purchase and Sale Obligations. Each FIT generator shall enter into a standard form FIT interconnection agreement and a standard form FIT power purchase agreement with the city the form of which shall be subject to the approval of the city attorney. It is a requirement of the FIT program that the FIT generator must sell and deliver to Glendale Water and Power 100% of the products from the electric generation facility. Notwithstanding the foregoing, the standard form FIT power purchase agreement may, in the city's discretion, specify a maximum quantity of energy and/or products that may be delivered from the FIT generator on an hourly, daily, monthly, or yearly or other basis. If the agreement so specifies, then the city shall have no obligation to purchase energy and/or products from the electric generation facility delivered in excess of the cap. F. Glendale Water and Power retains the right to install meters and obtain access to such meters at any part of the electric generating facility or the premises upon which it is located, including those meters located at the interconnection with the electric generating facility in order to completely assess the total load for that service. All costs of purchasing, installing and reading such meters and the cost of any other facilities required for the interconnection will be the responsibility of the applicant. The applicant shall be responsible for any engineering, construction, and administrative costs incurred by the city in connection with the application and the electric generation facility.
( Ord. 5806 § 28, 2013 )
Ask a question about Glendale law
Corpus searches the Glendale sections it holds and shows the ones that match, with their citations. Free, no sign-in.