SEC. 10-3.730 - TERRAIN DESIGN—CONTROL OF FILLS.

All fills shall be constructed in accordance with the approved grading plan and the specifications submitted by the soils engineer, and shall also meet the following requirements: a. All vegetable matter shall be removed from surface upon which fill is to be placed, and the surface shall then be plowed or scarified to a depth of at least 6" and until surface is free from uneven features which would tend to prevent uniform compaction by the equipment to be used. b. Where fills are made on hillsides or slopes, the slopes of the original ground upon which fill is to be placed shall be scarified deeply, or where the slope ratio of the original ground is steeper than 5 horizontal to 1 vertical, the bank shall be stepped or benched. Ground slopes flatter than 5 to 1 shall be benched when required by the soils engineer. c. After the foundation for the fill has been cleared, plowed or scarified, it shall be discoid or bladed until it is uniform and free from large clods, brought to proper moisture content, and compacted to not less than 85 percent relative compaction unless otherwise recommended by the soils engineer and approved by the City Engineer. d. Materials for the fill shall be as specified by the soils engineer and may be obtained from the excavation of banks, borrow pits or other approved sources. e. The selected material shall be placed in layers not to exceed 6" and compacted as set forth in subsection c. f. Field density tests shall be made of the compaction of each layer of the fill. g. All fill shall be placed under the field supervision of the soils engineer and, unless otherwise waived by the City. Engineer, reports and/or results of all tests shall be submitted to the City. h. The City Engineer may at any time perform soil tests, at the subdivider's expense, to evaluate the characteristics of the material in or being placed. i. The top layer shall consist of clean topsoil suitable for establishing the specified plant material. On-site topsoil shall be separately stockpiled if required by the City Engineer.

Ask a question about Hayward law

Corpus searches the Hayward sections it holds and shows the ones that match, with their citations. Free, no sign-in.