SEC. 8-17.08 - ABSORPTION STUDY.
An absorption study of any proposed development project shall be required for land secured financing. The absorption study shall be used A) as basis for verification that sufficient revenues can be produced; and B) to determine if the public financing of the public facilities is appropriate given the timing of the development. Additionally, the projected absorption rates will be provided to the appraiser for use in the appraisal required in Section V, above.