Sec. 2-11-212. - Construction plan.
A. Submittal requirements. Not less than 30 days prior to proposed commencement of any work in the PROW, company shall submit to the Director for his or her review a construction plan containing the following information: 1. Date for work completion. Company shall identify a completion date for the work and shall complete the system construction authorized by the PROW permit no later than the date specified in the permit. If company requires additional time to complete work, it shall so notify Director and Director may grant a work completion extension. 2. Facility information. The construction plan shall include photographs or artist renderings of all proposed facilities for the work area as well as their locations, dimensions, and color. Any modifications to construction plans must be reviewed and approved by Director before modifications can be implemented by company. In addition, company shall provide the Director with engineering base maps identifying company's existing underground and aerial utility facilities, poles, trench routes, and locations for above-ground equipment in the work area within the construction plan in both electronic form (digital or otherwise as specified by director) to the extent available and hard-copy form. 3. Hours of construction. All construction shall be accomplished and maintained between the hours specified by the Director. Construction shall not interfere with the existing or known future services of the City or private or public third parties. 4. Traffic control plan. At the request of Director, company shall furnish a detailed traffic control plan to the Director prior to the commencement of any construction activities which may interfere with traffic in arterial streets a traffic control plan. 5. Telephone contact. Company shall provide the Director with a telephone contact number, answered 24 hours a day during the construction period, to enable the Director to report any concerns regarding construction of the facilities. After business hours such calls will be routed to an on-call supervisor. In the event that the Director reports any concerns to company, company shall respond in a timely manner. Company shall immediately correct any adverse impact to the City's use or operations or the use or operations of a third party caused by company construction activities in the PROW at no cost to the City. Safety violations will be cause for immediate project shut-down. B. Emergency excavation. Nothing contained in this section shall be construed to prevent company from taking any action necessary for the preservation of life or property or for the restoration of interrupted service provided by company when such necessity arises during days or times when the Department is closed. In the event that company takes any action to excavate or cause to be excavated the PROW pursuant to this section, company shall apply for an emergency permit within 24 hours after the Department's offices first opened. The applicant for an emergency permit shall submit a written statement the basis of the emergency action and describe the excavation performed and work remaining to be performed. C. Blanket permits. The Director may issue blanket permits to company to make excavations for utility service connections, for the location of trouble in utility conduits or pipes and for making repairs thereto, or for emergency purposes. Blanket permits shall be issued on a yearly basis only, and shall authorize only excavations referred to in this section. Except as specifically provided otherwise in this chapter, excavations authorized by this section shall be subject to all fees and requirements of this chapter. D. Construction status report. During construction, company shall, at the request of the Director, submit to the Director regular progress reports describing in detail the status of construction in relation to the construction plan. The first report shall be submitted within seven days after commencement of construction and shall be updated days thereafter, as may be required by the permit. Work plans shall be provided in advance to the Director for review and approval. E. Notification. Company shall provide written notification to the Director of any construction and/or maintenance activities undertaken in PROW, whether undertaken pursuant to permit or otherwise, within five business days of commencement of such activities unless the activities have been previously reported to the Director. F. Approvals of construction plan. No permits shall be issued until the construction plan is reviewed pursuant to all relevant public health, safety, and welfare criteria and approved by the Director.
(Ord. No. 07-14, § 3, 5-22-07)
Ask a question about Irvine law
Corpus searches the Irvine sections it holds and shows the ones that match, with their citations. Free, no sign-in.