Sec. 7.65.030. - Limited lien as security for public improvements not required for two years or more.
A. The land divider may, in lieu of posting a security described in Section 7.65.010, enter into an agreement with the city to construct the required improvements in the future, securing such performance by granting the city a lien on the real property to be divided. Such agreements shall be known as "lien agreements." The use of lien agreements shall only be allowed if all requirements of this section are satisfied. B. Government Code Section 66499(a)(4) authorizes the city to enter into lien agreements if it is found by the city that it would not be in the public interest to require the installation of the required improvements sooner than two (2) years after the recordation of the map. C. Where the city finds that it would not be in the public interest to require the installation of the required improvements sooner than two (2) years after recordation of the map, the land divider may execute a lien agreement with the city at the time the land divider enters into an agreement with the city to construct required improvements pursuant to Chapter 7.30. D. A lien agreement may be used to substitute an existing security which was furnished under Section 7.65.010; provided, however, that use of a lien agreement as substitution for an existing security shall be at the city's sole discretion. The city will not accept a lien agreement from any land divider, either at the time of execution of the agreement to construct improvements, or as a substitute for existing security, if any individual lots have been sold, if any construction permits, including, but not limited to, any grading or building permits, have been issued on any of the property, or if construction of any of the required improvements has begun. Notwithstanding the above, the city may accept a lien agreement from any land divider as a substitute for existing security if grading has commenced on the land to be divided so long as the grading is in strict accordance with a valid grading permit and all the following are met: (1) There is no need for the city to construct the required improvements if the land divider's project is abandoned or delayed for any period of time or for any other reason; (2) The grading has no effect on the use, operation and maintenance of existing streets or highways, public or private; (3) The grading has not caused the modification or closure of any public access points, existing streets or highways, public or private; (4) Additional drainage improvement and/or erosion controls are not necessary and/or installed in the road right-of-way due to the grading; (5) Delay of the construction of the land divider's required improvements do not affect or delay the improvements of an adjacent land divider who has already commenced work on his or her required improvements. E. Lien agreements shall: (1) Be allowed only for Schedule "A", "B" and "E" maps. (2) Be allowed only where the land divider provides a title insurance policy and current title report from a title company approved by the city that documents that the land divider is the record owner of the real property to be divided and the real property to be divided is not subject to any mortgages, deeds of trust, or judgment liens. The title insurance policy and title report shall be issued within the sixty (60) days prior to the execution of the lien agreement. (3) Be in a form acceptable to and approved by City Attorney. (4) Be used to secure future improvements that would be required for Schedule "A", "B" and "E" maps. (5) Be used only when a land divider would be required by Chapter 7.30 to construct or agree to construct the required improvements. (6) Contain an itemization of the required improvements and an estimate of costs approved by the Public Works Director and shall specify that the land divider's or subsequent owner's obligation extends to the actual cost of construction of the required improvements if such costs exceed the estimate. (7) Be recorded with the County Recorder. The recorded lien agreement shall be indexed in the grantor index to the names of all record owners of the real property as specified on the map and in the grantee index to the city. (8) Be approved concurrently with the approval of the final map with a note of the lien agreement's existence placed on the map, except where the lien agreement is being substituted after final map approval for other security previously deposited pursuant to Section 7.65.010, in which case the lien agreement shall be signed and acknowledged by all parties having any record title interest in the property, as prescribed by Government Code Section 66436, consenting to the subordination of their interests to the lien agreement. F. From the time of recordation of the lien agreement, a lien shall attach to the property and shall have the priority of a judgment lien in an amount necessary to complete the required improvements. Under no circumstances shall the city agree to subordinate the lien. G. The lien agreement shall provide that the land divider shall substitute acceptable security for the lien agreement and commence to construct the improvements required pursuant to Chapter 7.30 within three (3) years following recordation of the map, or in the case of a lien agreement which has been substituted for existing security pursuant to Section 7.65.010 within three (3) years following recordation of the lien agreement. H. The time for substitution of acceptable security and commencement of construction of the required improvements in subsection (G) of this section, may be extended up to three (3) times, by the Public Works Director only upon forms and terms approved by the City Council. Each extension shall be for a period not to exceed one (1) year. However, the City Council may grant additional time extensions, as it deems appropriate, for substitution of acceptable security and commencement of construction of the required improvements pursuant to agreements secured either by: (1) Lien agreements executed at the time of recordation of the map; or (2) Lien agreements substituted for an existing security furnished under Section 7.65.010. For each extension of time under this subsection, the land divider shall provide a title insurance policy and current title report from a title company approved by the city that documents that the land divider is the record owner of the real property to be divided and the real property to be divided is not subject to any mortgages, deeds of trust, or judgment liens. The title insurance policy and title report shall be issued within the sixty (60) days prior to request for an extension of time. I. No individual lots may be sold while the lien agreement is in place. However, fee title to the entire property encumbered by the lien agreement or to all lots designated on any individual final map which is encumbered by the lien agreement, may be sold in the aggregate to a single purchaser, provide that the proposed purchaser must, prior to assuming title to the property, either: (1) Execute a new lien agreement in a form acceptable to the city which will encumber the property to be conveyed, specifying the respective obligations of the owners of property subject to the original and new lien agreement; or (2) Provide acceptable alternative security for the required improvements to be constructed as a condition to development of the property conveyed, pursuant to Section 7.65.010. Any new lien agreement must require that acceptable security be substituted therefor, and the improvements secured thereby commenced by the same date provided in the lien agreement with the original owner, unless such date shall be extended by the City Council as provided in subsection (H) of this section. J. At the time the City Council approves a lien agreement, the land divider shall provide a cash deposit in the amount of twelve thousand dollars ($12,000) or as modified by resolution to the city for the purpose of reverting the property to acreage if the land divider breaches the terms of the lien agreement. In addition, at such time as title to any property subject to a lien agreement shall be conveyed, the transferee thereof, if such transferee executes a new lien agreement to secure construction of the improvements imposed upon such property as described in subsection (I) of this section, shall provide a substitute cash deposit in the amount of twelve thousand dollars ($12,000) established or as modified by resolution to the city for the purpose of reverting the property to acreage if the land divider breaches the terms of the lien agreement. Any unused portion of any such deposit shall be refunded to the land divider following completion of such reversion. If the costs of reverting the property to acreage exceed twelve thousand dollars ($12,000) or as modified by resolution, the land divider shall pay such additional costs to the city prior to recordation of the reversion to acreage map. K. The lien agreement shall only be released upon substitution of acceptable security for the lien agreement under Section 7.65.010 in order begin construction of the required improvements, or upon recordation of a reversion to acreage map. L. In no instances shall the lien agreement compel the city to construct the required improvements.
Ask a question about Jurupa Valley law
Corpus searches the Jurupa Valley sections it holds and shows the ones that match, with their citations. Free, no sign-in.