For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 2.84.110 — Contract performance

Long Beach Municipal Code (Supp. No. 53, Update 1: codified through Ordinance No. ORD-26-0027, enacted October 13, 2026) · Long Beach Municipal Code § 2.84.110

Corpus is an independent public-information project, not the official City of Long Beach website. Stable reference: corpuslaw.us/code/e9366f65-a11b-4742-a9a7-4e948643bc4a

2.84.110 - Contract performance.

The JOC contractor must perform a minimum of fifteen percent (15%) of the contract work for a project, with no more than eighty-five percent (85%) of the work done by subcontractors. All subcontractors used by the primary contractor must be pre-approved by the City, and at a minimum be required to be licensed, hold liability insurance, and have sufficient relevant experience.

(ORD-21-0038 § 2, 2021; ORD-16-0008 § 1, 2016)

Ask a question about Long Beach law

Corpus searches the Long Beach sections it holds and shows the ones that match, with their citations. Free, no sign-in.