§ 2.87.050 — Subcontractor—Substitution authorization

Long Beach Municipal Code (Supp. No. 53, Update 1: codified through Ordinance No. ORD-26-0027, enacted October 13, 2026) · Long Beach Municipal Code § 2.87.050

Corpus is an independent public-information project, not the official City of Long Beach website. Stable reference: corpuslaw.us/code/8413ad13-d0f3-4271-bd3f-72274a8b732c

2.87.050 - Subcontractor—Substitution authorization.

The City Manager may give his consent to a substitution of a subcontractor under any of the following conditions: A. If the subcontractor named in the bid, after having a reasonable opportunity to do so, fails or refuses to execute a written contract when said written contract, based upon the general terms, conditions, plans and specifications for the project involved, or the terms of such contractor's written bid, is presented to him by the general contractor; B. If the subcontractor listed fails, refuses or neglects, within a reasonable time after requested by the general contractor, to commence labor or service to be rendered by such subcontractor, or to diligently complete the service or labor after commencement thereof; C. If the work being performed by the subcontractor is not being prosecuted in a manner satisfactory to the City Engineer.

(Prior code § 7110.3)

Ask a question about Long Beach law

Corpus searches the Long Beach sections it holds and shows the ones that match, with their citations. Free, no sign-in.