Sec. 32B.7. - Imposition, calculation and collection of impact fees.

(a) Impact fees shall be imposed as a condition of all development projects. No tentative or final subdivision map, parcel map, grading permit, building permit, final inspection or certificate of occupancy shall be approved unless the provisions of this section have been fulfilled. (b) Impact fees shall be imposed by affixing the following language to the development approval: Approval of this development project is conditioned upon payment of all applicable impact fees and connection fees in the manner provided in chapter 32B of the Oceanside City Code. (c) The calculation of impact fees due shall be based upon the impact fee schedule in effect at the time of issuance of a building permit. Impact fees for non-residential development projects shall be collected at the time of issuance of a building permit. Fees for residential development projects shall be collected in accordance with Government Code section 66007. (d) Subject to Government Code section 66007, no building permit shall be issued until all impact fees due for the development project have been paid. (e) Notwithstanding the provisions of subsections (c) and (d) above; requests for the deferral of development impact fees may be submitted to the city engineer under the following procedures: (1) A written request shall be made no later than forty-five (45) days prior to issuance of a building permit. (2) A request shall be made only for a residential or non-residential development project that has received final discretionary action by the city and that is in compliance with all environmental requirements due prior to issuance of a building permit. (3) Unless otherwise prohibited by law, a request shall be accompanied by a non-refundable payment of a five hundred dollars ($500.00) processing fee, and the applicant shall be responsible for paying all costs associated with recording an agreement should the request be approved. (4) If a request for deferral of development impact fees is approved, the applicant, and the owner of the project property, if different, shall enter into a "fee deferral agreement" with the city, in a form acceptable to the city attorney, agreeing to a payment plan for the approved deferred fees. The applicant's obligations under the fee deferral agreement shall be secured by either a lien on the project property or an irrevocable letter of credit. a. Subject to subsection 32B.7(e)(4)b., below, the fee deferral agreement shall constitute a lien on the project property. The city manager is authorized to execute the agreement on behalf of the city and to cause the agreement to be recorded with the San Diego County Recorder's Office. The lien may be released when the obligation is paid in full. b. As an alternative to recording the fee deferral agreement that constitutes a lien on the project property, the applicant may, prior to and as a condition of issuance of the building permit, provide an irrevocable letter of credit pursuant to procedures established by the city engineer. The amount of the letter of credit shall be calculated per the fees in effect at the time of execution of the agreement with the city; however, the city may require that the amount of the letter of credit be increased if there is an increase in fees during the time the agreement is in effect. (5) The amount of any deferred fees shall be calculated according to the applicable fee schedule set by resolution of the city council in effect at time of payment. All fees subject to the payment plan agreement shall be paid in full by the earlier of: (1) the date of the final inspection, or (2) the date the certificate of occupancy or temporary occupancy is issued. A utility release and installation of a water meter(s) to serve the development shall only be made after payment in full of water system buy-in fees and wastewater system buy-in fees. (6) The city's approval of a fee deferral is not transferrable to any other project.

(Ord. No. 88-45, § 1, 12-14-88; Ord. No. 91-11, § 7, 2-27-91; Ord. No. 02-OR331-1, § 1, 5-8-02; Ord. No. 18-OR0479-1, § 1, 9-19-2018; Ord. No. 25-OR0670-1, §§ 4—6, 12-3-2025)