18.76.110 - Interim management plans.
A. Within ninety days of a surface mining operation becoming idle, the operator shall submit to the planning division a proposed interim management plan (IMP). The proposed IMP shall fully comply with the requirements of SMARA, including but not limited to all site approval conditions and shall provide measures the operator will implement to maintain the site in a stable condition, taking into consideration public health and safety. The proposed IMP shall be submitted on forms provided by the planning division and shall be processed as an amendment to the reclamation plan. IMPs shall not be considered a project for the purposes of environmental review. B. Financial assurances for idle operations shall be maintained as though the operation were active, or as otherwise approved through the idle mine's IMP. C. Upon receipt of a complete proposed IMP, the planning division shall forward the IMP to the State Department of Conservation for review. The IMP shall be submitted to the State Department of Conservation at least thirty days prior to approval by the planning commission. D. Within sixty days of receipt of the proposed IMP, or a longer period mutually agreed upon by the director of development services and the operator, the planning commission shall review and approve or deny the IMP in accordance with this chapter. The operator shall have thirty days, or a longer period mutually agreed upon by the operator and the director of development services to submit a revised IMP. The planning commission shall approve or deny the revised IMP within sixty days of receipt. If the planning commission denies the revised IMP, the operator may appeal that action to the city council. E. The IMP may remain in effect for a period not to exceed five years, at which time the planning commission may renew the IMP for another period not to exceed five years, or require the surface mining operator to commence reclamation in accordance with its approved reclamation plan.
(Ord. 1285 § 1 (part), 1999)
Ask a question about Rialto law
Corpus searches the Rialto sections it holds and shows the ones that match, with their citations. Free, no sign-in.