2.48.310 - Acquisition of design-build services.
A. Policy. In accordance with Chapter 4, Part 3, Division 2 of the California Public Contract Code sections 22160 through 22169, acquisition of design-build services may be procured for the construction of a public project. The director is authorized to establish policies and procedures for implementation of design-build procurement within the guidelines in this section. B. Procurement. Construction of public projects may be implemented in accordance with the design-build project delivery method by undertaking an RFP process. Notwithstanding the foregoing, the city may prequalify bidders through an RFQ process prior to the RFP process. The RFP must contain, at a minimum, the following elements: 1. The procedures to be followed for submitting proposals, the criteria for evaluation of the proposals and their relative weight, the procedure for selection of a contractor and the timing for making awards. 2. The proposed terms and conditions for the design-build contract. 3. The project requirements, including as appropriate, capacity, durability, production standards, ingress and egress requirements, or other criteria for the intended use of the project, expressed in conceptual documents, performance-oriented preliminary drawings, outline specifications and other documents provided to the contractor by the city establishing the project's basic elements and scale, and their relationship to the work site suitable to allow the contractor to submit a proposal. 4. A description of the project approach, work plan or other submittals to be submitted with the proposal, with guidance as to the form and level of completeness required. 5. A schedule for planned commencement and completion of the project. 6. Any other information that the city, in its discretion chooses to supply, including without limitation, surveys, soils reports, drawings or models of existing structures, environmental studies, photographs, or references to public records. C. Evaluation and selection. Once received, proposals shall be submitted for review by a selection committee. Clarifications may be required to ensure proposals are responsive to the RFP. Clarifications may require revised cost and/or technical proposals. The following criteria may be utilized in selecting a contractor for award of a design-build contract: 1. An evaluation of references provided with respect to responsiveness, quality of work, timeliness and overall performance. 2. An evaluation of overall quality, capability, resource availability and financial stability of the contractor. 3. An evaluation of the contractor's experience, training and qualifications. 4. Consideration of items such as proposed design approach, initial and/or life cycle costs, project features, quality, capacity, schedule, and operational and functional performance of the facility. 5. The extent to which the contractor's proposal meets the requirements set forth in the RFP. 6. Analysis of the cost relative to the contractor's ability to meet the requirements set forth in the RFP. Depending on the number of proposals received, the selection committee may develop a "short list" of top ranked contractors. The selection committee may require "short listed" contractors to submit to an interview and/or make a presentation to establish a final ranking. The selection committee will then begin negotiations with the top ranked contractor. The negotiations may include but not be limited to project costs, scope, and schedule. If negotiations are unsuccessful, negotiations will cease with the top ranked contractor and may begin with the next highest ranked contractor. The city reserves the right to reject all proposals, select by proposal review only or interview as needed. The city's selection committee shall select and recommend to the city council for contract award a contractor providing the best value to the city.
(Ord. No. 1662, § 2, 9-28-21)
Ask a question about Rialto law
Corpus searches the Rialto sections it holds and shows the ones that match, with their citations. Free, no sign-in.