Sec. 33-254. - Coordination with other projects in public rights-of-way.
To the maximum extent possible and as permitted by law, an applicant shall design and schedule its Work so as to coordinate its Work with other persons installing, constructing, or maintaining wireless facilities and other infrastructure in the public right-of-way and with the City.
(Ord. No. NS-2954, § 3, 9-18-18)