§ 20-54.050 — Time limits and extensions
Code of Ordinances, City of Santa Rosa, California (Code 2026-09-15: eCode360 publication current through Ord. No. 2026-014 adopted September 15, 2026 (scraped 2026-11-20)) · Santa Rosa Code of Ordinances § 20-54.050
Corpus is an independent public-information project, not the official City of Santa Rosa website. Stable reference: corpuslaw.us/code/069eb7f7-2347-49f7-9f32-be1da291974a
§ 20-54.050: Time limits and extensions.
A. Time limits. 1. Unless conditions of approval or other provisions of this Zoning Code establish a different time limit, any permit or approval not exercised within 24 months following the date on which the permit or approval was granted shall automatically expire and shall be void, except when associated with an approved Tentative Map in compliance with Subsection A.2, or where an extension of time is approved in compliance with Subsection B. 2. All approved project entitlements, such as a Conditional Use Permit or Hillside Development Permit, associated with an approved Tentative Map shall remain effective concurrent with the period of time the Tentative Map is in effect. If an extension of time is requested for the associated Tentative Map, a similar extension of time for all associated entitlements shall be required and shall be processed concurrently with the Tentative Map extension request. 3. The permit or approval shall not be deemed "exercised" until the permittee has substantially commenced the approved use on the site in compliance with the conditions of approval or a Building Permit has been issued involving the permit or approval and construction under the permit has commenced and is diligently pursued toward completion on the subject property. 4. The permit or approval shall remain valid after it has been exercised as long as a Building Permit is active for the project, or a final building inspection or Certificate of Occupancy has been granted. 5. If a project is to be developed in approved phases, each subsequent phase shall be exercised within 24 months from the date that the previous phase was exercised, unless otherwise specified in the permit or approval, or the permit or approval shall automatically expire and shall be void, except where an extension of time is approved in compliance with Subsection B. B. Extensions of time. Upon written request by the applicant, the Director may extend the time limit established by Subsection A for a permit or approval to be exercised. 1. The applicant shall file a written request for an extension of time with the Department at least 30 days before the expiration of the permit or approval, together with the filing fee required by the Council's Fee Schedule. Expiration of the permit or approval will be stayed until the decision on the extension request if the request is filed 30 days before the original expiration. 2. The Director shall determine whether the applicant has made a good faith effort to exercise the permit or approval. The burden of proof is on the applicant to establish, with substantial evidence beyond the control of the applicant (e.g., demonstration of financial hardship, legal problems with the closure of the sale of the parcel, poor weather conditions in which to complete construction activities, etc.), why the permit or approval should be extended. 3. The Director may grant up to four 12-month extensions to the expiration date of the original approval only upon the Director's determination that conditions of the site and in the vicinity are substantially the same as when the permit or approval was originally granted. C. Effect of expiration. After the expiration of a permit or approval in compliance with Subsection A (Time limits), above, no further work shall be done on the site until a new permit or approval is first obtained.
( Ord. 3677 § 1, 2004 ; Ord. 3995 §§ 13, 14, 2012 ; Ord. 2026-006 , 4/21/2026 )
Ask a question about Santa Rosa law
Corpus searches the Santa Rosa sections it holds and shows the ones that match, with their citations. Free, no sign-in.