§ 22.0817 — Liability for Increased Costs

San Diego Municipal Code (City Clerk PDFs, pages revised through October 2026) · San Diego Municipal Code § 22.0817

Corpus is an independent public-information project, not the official City of San Diego website. Stable reference: corpuslaw.us/code/82cfdf68-f268-44e6-bfc2-7dbe7240c7ea

§22.0817 Liability for Increased Costs

Any bidder or contractor who enters into a contract, either directly as a prime contractor or indirectly as a subcontractor, during a period of suspension or debarment imposed upon that bidder or contractor, shall be liable to the City for increased costs incurred as a result of replacing the debarred or suspended bidder or contractor. (“Liability for Increased Costs” added 8-10-2016 by O-20715 N.S.; effective 9-9-2016.)

Ask a question about San Diego law

Corpus searches the San Diego sections it holds and shows the ones that match, with their citations. Free, no sign-in.