§ 18.06.040 — Types of work covered by a grading permit

Municipal Code, City of Temecula, California (legislation through Ord. No. 2026-04 adopted April 14, 2026) · Temecula Municipal Code § 18.06.040

Corpus is an independent public-information project, not the official City of Temecula website. Stable reference: corpuslaw.us/code/fe7dc351-18c2-4aa0-8243-c343dcb9197a

§ 18.06.040: Types of work covered by a grading permit.

A. The types of work covered by a grading permit include the following: 1. Mass, Rough or Precise Grading. The city engineer may issue a grading permit for mass, rough or precise grading work upon completion of an application in accordance with the Engineering and Construction Manual. The issuance of building permits by the department of building and safety shall be determined as follows: a. Building permits may be issued for a site graded under a grading permit for precise grading work, upon completion and approval of the rough grade inspection, as specified in and subject to the requirements of the Engineering and Construction Manual. b. Building permits shall not be issued for a site graded under a grading permit for rough grading work, unless a precise grading plan has been approved. 2. Borrow Sites. A grading permit shall not be issued when, in the opinion of the city engineer, a significant amount of borrow or waste material is to be removed from a grading site for commercial purposes, unless a conditional use permit in accordance with Chapter 17.04, "Permits" of the Temecula Municipal Code has been issued for the operation of a borrow pit on the grading site. 3. Stockpiling. Upon approval by the planning commission, a grading (stockpile) permit may be issued for the stockpile of soil materials on a lot or parcel provided that the soil materials shall be removed from the site or compacted and graded thereon under a subsequently issued mass, rough or precise grading permit within six months of issuance of a stockpile permit, unless modified by the planning commission in accordance with the Engineering and Construction Manual. 4. Erosion and Sediment Control (ESC). All grading plans, regardless of the date of submittal, shall include an erosion and sediment control plan designed to limit erosion and sediment discharges of all disturbed portions of the property and to minimize the transport of soil onto adjacent properties or into stormwater conveyance systems in accordance with the provisions of Chapter 18.18 of this title and the Engineering and Construction Manual. The ESC work shall be covered under the grading permit. 5. Administrative Clearing. No person shall commence any clearing and grubbing operation without first obtaining a grading (administrative clearing) permit in accordance with the Engineering and Construction Manual. 6. Rock Blasting. No rock blasting shall be permitted until a pre-blast survey of the surrounding property is conducted to the satisfaction of the city engineer. During rock blasting, seismic recordings shall be taken for all blasts at locations and levels approved by the city engineer. All blasting shall conform to the requirements of the city engineer, as specified in and subject to the requirements of the Engineering and Construction Manual. 7. Paving. For on-site (private) development, no person shall construct concrete or bituminous pavement surfacing on natural or existing grade in excess of five thousand square feet for any commercial, industrial, multiresidential or other parking lot, without a valid grading permit for such paving operation. This excludes developments consisting of a single-family residence. Maintenance and repaving of existing paved sections shall be exempt from this requirement. 8. Watercourse Alteration. No person shall alter an existing watercourse, channel or revetment (by excavating or placing fill, rock protection or structural improvements therein) without an applicable state agency approval and a grading permit unless: a. The requirement for a grading permit is waived by the city engineer; b. The grading is performed as interim protection in an emergency to prevent flooding; or c. A separate improvement plan for such alteration is approved by applicable state agencies and the city engineer.

( Ord. 13-01 § 4 )

Ask a question about Temecula law

Corpus searches the Temecula sections it holds and shows the ones that match, with their citations. Free, no sign-in.